11.3 Checklist before commissioning

11.4 Checklist during commissioning

11.5 To perform a test run

RXQ-A_ARXQ-A
R32 split series
4P513661-11P – 2021.11
During test operation, the outdoor unit and the indoor units will start up. Make
sure that the preparations of all indoor units are finished (field piping, electrical
wiring, air purge, ...). See installation manual of the indoor units for details.
1 After the installation of the unit, check the items listed below.
2 Close the unit.
3 Power up the unit.
The indoor unit is properly mounted.
The outdoor unit is properly mounted.
The system is properly earthed and the earth terminals are tightened.
The power supply voltage matches the voltage on the identification label of the unit.
There are NO loose connections or damaged electrical components in the switch box.
There are NO damaged components or squeezed pipes on the inside of the indoor and
outdoor units.
There are NO refrigerant leaks.
The refrigerant pipes (gas and liquid) are thermally insulated.
The correct pipe size is installed and the pipes are properly insulated.
The stop valves (gas and liquid) on the outdoor unit are fully open.
Drainage
Make sure drainage flows smoothly.
Possible consequence: Condensate water might drip.
The indoor unit receives the signals of the user interface.
The specified wires are used for the interconnection cable.
The fuses, circuit breakers, or locally installed protection devices are installed according to
this document, and have NOT been bypassed.
To perform an air purge.
To perform a test run.
INFORMATION
If the unit runs into an error during commissioning, see the service manual for the
detailed troubleshooting guidelines.
Prerequisite: Power supply MUST be in the specified range.
11
Commissioning
|
Installer reference guide
53

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rxq25amv1bArxq25amv1bArxq35amv1bArxq-aRxq-a

Table of Contents