4. INSTALLATION
4-8. Installing the solenoid valve assembly
4-9. Connecting the air tubes [4]
Plugs 4
4-10. Installing the air hose [5]
10
Connect as shown in
the illustration while
checking the marks.
Branch unions Y
Close
Open
2564B
BAS-342G
Install underneath the work table.
to "3. Table processing diagram" for the
installation positions.)
(1) Solenoid valve assembly
(2) Washers [2 pcs.]
(3) Wood screws [2 pcs.]
NOTE:
Make sure that the solenoid valve
assembly does not touch the control
box or the leg of the table.
2562B
1.
Close the cock (1).
2. Turn the nut (3) at the end of the air hose (2) and connect it
to the valve (4).
3. Open the cock at the compressor.
* Check that no air is leaking from the connection of the
valve (4) and air hose (2).
4. Open the cock (1).
(The meter pointer will turn clockwise.)
NOTE:
Turn the cock (1) gently to open it.
5. Adjust the air pressure. (Refer to the next page.)
(
Refer
2563B

Advertisement