6. Installation and commissioning
6.1. General information
Keep the protective caps on all hydraulic con-
nectors in place until assembly. This protects the
components from contamination.
Check that all the bolts and hydraulic connec-
tors are tight. The control cabinets are always
pressure-tested and checked before delivery.
However, during transport threaded connections
can become loose and therefore it is necessary
to check them before pressurizing the system.
6.2. Control cabinet installation
The control cabinet is meant to be mounted on
a wall or plinth intended for it.
6.3. Power connection
All power connections must be made by a pro-
fessional. Main power must be turned off before
connecting the power supply to the cabinet. The
power connection is done in accordance with
the diagrams shown in Figure 8.
INCOMING SUPPLY
3 x 400/230V, 50 Hz
MAX 16A
Figure 8. Connecting power supply