STEP 4 - Inverter country standard, Input configuration and Meter
configuration (Dynamic Feed-in Control)
From the moment that the grid standard is set, you have 24 hours to make any changes to the
value, after which the "Country Select > Set Std." functionality is blocked, and the remaining
time will have to be reset in order to have the 24 hours of operation available again in which
to select a new grid standard (follow the procedure "Resetting the remaining time for grid
standard variation" described in the relevant section).
If a 3PH energy meter (ABB B23, B24) is used in the system as single-phase inverter, it will be
necessary to select ABB 3PH and the phase to which the inverter is connected.
- Country standard: selection of grid standard:
Set the grid standard of the country in which the inverter
is installed.
- Input mode:
(See the relevant section of this manual to know how
set the input mode)
1. Indipendent
2. Parallel
- Meter:
When a meter device is connected to the inverter, it's
requested to select the meter model:
1. None (where system is installed without meter)
2. REACT-MTR-1PH (single-phase)
3. ABB 1PH (single-phase)
4. ABB 3PH (three-phase)
- 104 -