FusionCol8000-C210 In-room Chilled Water Smart
Cooling Product
User Manual
Step 5 Tap Yes. The screen for component commissioning is displayed, as shown in
Figure
Figure 5-19 Fan commissioning
Step 6 View the commissioning result.
●
●
Issue 05 (2022-12-15)
NO TE
● If the system is not configured with the electric heater components, the electric heater
commissioning item will not appear on the screen.
● If the heating function and humidification function are disabled, you cannot select the
electric heater and humidifier items.
● All the items are selected by default if you enter the screen for selecting commissioning
items for the first time. You can deselect any commissioning items except "Indoor fan
commissioning."
5-19.
NO TE
The fan commissioning item is mandatory. After commissioning for a component succeeds,
the system automatically performs commissioning for the next component you selected. If
commissioning fails, wizard-based startup ends.
Figure 5-20
is displayed if component commissioning succeeds.
Figure 5-20 Commissioning succeeded
The screen shown in
fails, which ends commissioning in the wizard-based startup.
Copyright © Huawei Digital Power Technologies Co., Ltd.
Figure 5-21
is displayed if component commissioning
5 Power-On Commissioning
100