Ring-Main And Circuit-Breaker Panels: Operating The Three-Position Switch - Siemens 8DJH Series Installation And Operating Instructions Manual

Medium-voltage switchgear
Table of Contents

Advertisement

Operation
Connecting the feeder to the busbar:
Initial situation (three-position switch
OPEN, earthing switch OPEN)
Disconnecting the feeder from the busbar:
Initial situation (three-position switch
CLOSED, earthing switch OPEN)
106
16.3

Ring-main and circuit-breaker panels: Operating the three-position switch

Push control gate upwards
Push control gate upwards
Revision 03 * INSTALLATION AND OPERATING INSTRUCTIONS 8DJH * 500-8067.9
Switch three-position switch to
CLOSED position (insert operating
lever and turn approx. 70° clockwise)
Switch three-position switch to OPEN
position (insert operating lever and turn
approx. 70° counter-clockwise)
Remove operating lever (control gate
returns to its initial position)
Remove operating lever (control gate
returns to its initial position)