SMA SUNNY BOY 240 Instruction Manual page 21

Table of Contents

Advertisement

SMA Solar Technology AG
Figure 6:
Dimensions of the inverter and the drill holes for mounting
Recommended clearances:
☐ When using an AC cable of 1.40 m: min. 50 mm to max. 1.10 m
☐ When using an AC cable of 2.0 m: min. 50 mm to max. 1.70 m
☐ Using the AC field plug allows for greater distances between two inverters (see Section 6.6.1
"Assembling the AC Field Plug", page 34).
☐ Observe recommended clearances to the inverters or other objects.
Figure 7:
Recommended clearances with AC cable
Minimum Clearance between Inverter and PV Module Bottom Side:
Damage to the PV module due to insufficient clearance between the inverter and the
PV module bottom side
If you have to ground the enclosure, allow for a minimum clearance from the inverter to the bottom
side of the PV module, if necessary.
Permitted Mounting Position:
Risk of electric shock due to ingress of moisture
During mounting, make sure that the connection area of the inverter remains dry.
As soon as the connector and protective cap are plugged in, the connection area will be protected
from moisture ingress. Thus, the inverter complies with degree of protection IP65.
Installation Manual
SMG-SB240-IA-en-11
5 Mounting