SECTION TWO Installing the 2201
Page 12
2.
Unpack the carton, and compare its contents with those
on the packing list and what you ordered.
3.
The shipping carton contains the following parts:
Northstar 2201 or 2201/NMEA
3 mounting screws (10-32 UNF) and washers for deck
mounting
50-foot data/power cable with waterproof 7-pin
connector (Northstar part number 2201-CA)
DB9 connector kit (for 2201/NMEA only)
Northstar 2201 and 2201/NMEA Installation Manual
(GM2201, Rev. A)
3 mounting screws and 3 washers,
(supplied for deck mounting)
50-foot 2201-CA data/power cable with
connector

Figure 1: Northstar 2201 and 2201/NMEA components

4.
After inspecting the components, review all the
installation requirements, including:
the physical requirements (spacing, location with
regard to other equipment, etc.)
the electrical and electronic requirements
(interference between other pieces of equipment,
antennas, power requirements, etc.)
5.
Preview/survey the vessel's layout and existing
equipment.
6.
Select the desired mounting location; for details, see
"Choosing a mounting location" on page 13.
7.
Fabricate the appropriate wiring; for details, see "Using
the 2201-CA cable" on page 17.
8.
Connect the 2201 to the desired instrument and to
power: For the 2201 binary, see "Connecting the 2201
Northstar 2201 or 2201/
NMEA WAAS Pod
DB9 connector (for 2201/NMEA units)
2201 INSTALLATION MANUAL, Revision B