38 | Commissioning the heating system
5.4

Start-up report

B Sign all completed start-up work and enter the date.
Start-up work
1.
Pressure test on boiler supplied in loose sections
2.
Filling the heating system
3.
Perform a leak test on the heating system
• Record the filling water quantity and
composition in the operator's log (included
with the technical documentation).
4.
Check the position of the hot gas baffles
(the 16-section boiler has no hot gas baffles)
5.
Check the fuel line for leaks
6.
Start up the control unit
7.
Starting the burner
8.
Check the flue gas temperature
9.
Check flue for tightness
10.
Check the soundness of the hot gas side
11.
Enter the fuel used in the table provided in the
operating instructions.
12.
Provide the system user with information and
hand over all relevant technical documentation
13.
Confirm professional commissioning
Company details/signature/date
Tab. 13 Start-up report
6 720 803 940 (2010/03)
Page
Page 20
Page 25
Page 25
Page 36
See control unit
documentation.
See burner documentation
Comments
(signature)
UNI 7000 F

Advertisement

Table of Contents
loading

Table of Contents