Setting Up The Boiler Block (When Supplied As A Pre-Assembled Block); Inserting The Feed Pipe (Parts Case) - Bosch UNI 7000 F Installation And Servicing Instruction

High efficiency cast iron
Table of Contents

Advertisement

18 | Installation
4.5
Setting up the boiler block (when
supplied as a pre-assembled block)
B Cut through the straps.
B Remove pallet.
DANGER: Risk to life due to falling loads!
B Observe the transport information on the
data sheet (attached to boiler block)
when lifting the boiler block off the
pallet.
1
Fig. 19 Boiler block on pallet
1
Pallet
2
Securing straps
Level the boiler block vertically and horizontally on the
base/silencing plinth. Use the boiler section foot wedges
provided for this purpose.
Once the boiler block is levelled, remove the transport
stay from the upper and lower hubs.
The following pages describe the
installation of the feed pipe, sensor well and
outer steam tube. The installation steps are
the same, regardless of whether delivery is
as a pre-assembled block or in loose
sections.
6 720 803 940 (2010/03)
3
Fig. 20 Removing transport stay
1
Upper hub
2
Lower hub
3
Transport stay
4.6
2
On boilers with 9 – 11 sections the feed pipe is in 2
parts; on boilers with 12 – 16 sections, it comes in 3
6 720 648 663-16.1T
parts.
B Push the flat gasket over the feed pipe.
B Push the feed pipe from the front into the upper
boiler hub.
B Close off with dummy flange.
B Place the lug on the feed pipe connection endplate
into the recess on the upper boiler hub.
1
2

Inserting the feed pipe (parts case)

To ensure the discharge openings of the
feed pipe are at the correct angle, the lug on
the feed pipe connection endplate must be
placed in the recess on the upper boiler
hub.
6 720 648 663-17.1T
UNI 7000 F

Advertisement

Table of Contents
loading