Initial testing of the ALCR-DIN should be done with the Remote Loop In
and Remote Loop Out jumper installed.
1. Turn On the circuit breaker in the emergency panel for the
controlled circuit. The Status LED on the ALCR-DIN illuminates red.
With only the emergency circuit On (normal power should be Off),
the emergency lighting should be activated.
2. Temporarily disconnect and cap the wire lead connected to the
Normal Control Sense input on the ALCR-DIN. This disables the
normal control function and allows exclusive testing of the
emergency On functionality.
3. Turn On the circuit breaker in the normal panel for the controlled
circuit. The Status LED on the ALCR-DIN illuminates green,
indicating that normal power is present and emergency lighting is
not required.
4. Confirm the automatic emergency On functionality by turning Off
the circuit breaker in the normal panel. The connected emergency
lighting should immediately turn On again and the Status LED on
the ALCR-DIN illuminates red.
5. With the normal circuit breaker secured Off, reconnect the Normal
Control Sense wire.
6. Turn On the normal circuit breaker. The ALCR-DIN should now
behave as described in
Note:
Automatic Load Control Relay, see
page 5
Test on page 8
ALCR-DIN
If you have installed a remote activation input to the
to confirm proper installation and see
to test the connection.
Examples of Use on page 9
Remote Activation Input on
Page 7 of 12
.