Installing the gas
pressure regulator
Final inspection
Next task
HON 380 gas pressure regulator with HON 673/674 controller
Proceed as follows:
Figure
Conduct a final inspection to check whether the following criteria are met:
All screwed connections on the device and supply lines are securely fas-
tened.
If ...
at least one criterion is not met
all criteria are met
Proceed as follows:
Installing the device connections (see page 30)
Transport and installation
Step
Description
1
Remove the transport panels.
2
Transport the device to the location
where it will be installed.
The device needs to be installed in
the piping in a horizontal and level
position. If you want to use a differ-
ent installation position, consult
with the manufacturer first.
Pay attention to the direction of
flow for the gaseous fluid as
marked on the body.
3
Secure and support the device's posi-
tion in such a way that the device can
be installed in the piping without any
stress and that the piping's weight will
be supported as well.
4
Install the flange gaskets.
5
Screw down the flange crosswise in
the specified order. When doing so,
make sure to observe the torques
specified by the flange gaskets' man-
ufacturer.
then ...
you should correct the error before proceed-
ing with the next task.
you may proceed with the next task.