Heat-N-Glo TIARA I-CE Installer's Manual page 21

Table of Contents

Advertisement

1. Position the firestops.
2. Place the heat shield
to the top.
3. Continue the flue run.
1. Cut the 254 mm by
254 mm hole.
2. Add the new framing
members.
HEAT SHIELD
INTERIOR
FIRESTOP
Figure 16. Heat Shield, Interior & Exterior Firestops
For Vertical Runs - One ceiling firestop is REQUIRED
at the hole in each ceiling through which the flue passes.
To install firestops for vertical runs that pass through
ceilings:
• Position a plumb bob directly over the center of the
vertical flue component.
• Mark the ceiling to establish the centerpoint of the
flue.
• Drill a hole or drive a nail through this centerpoint.
• Check the floor above for any obstructions, such as
wiring or plumbing runs.
• Reposition the stove and flue system, if necessary, to
accommodate the ceiling joists and/or obstructions.
• Cut an 254 mm X 254 mm hole through the ceiling,
using the centerpoint previously marked.
• Frame the hole with framing lumber the same size as
the ceiling joists.
NOTE: There must be NO INSULATION or other
combustibles inside the framed firestop opening.
254 mm
NEW
FRAMING
MEMBERS
CEILING
Figure 17. Hole and New Framing Members
TRIM HEAT
SHIELD IF TOO
LONG, ADD TO
SHIELD IF TOO
SHORT
EXTERIOR
FIRESTOP
254mm
CHIMNEY
HOLE
EXISTING CEILING
JOISTS
25

Advertisement

Table of Contents
loading

This manual is also suitable for:

Tiara ii-ce

Table of Contents