6  Preparation for Installation

6.2 Preparation for Mounting without Base

6.2.1

Position of the Mounting Holes on the Sunny Central

The fixtures in the support surface can be prepared prior to installing the Sunny Central.
The Sunny Central must be attached to the support surface by means of six bolts. Mounting holes for attaching the inverter
to the foundation or the base are located in the inverter floor.
Figure 13: Position of the mounting brackets on the Sunny Central
Position
Designation
A
Mounting holes for mounting on a base or foundation
B
Mounting holes for mounting on a base
C
Mounting holes for mounting on a foundation
6.2.2

Drilling Mounting Holes in the Foundation

1. Mark the positions of the mounting holes on the foundation corresponding to the mounting brackets.
2. Drill mounting holes at the marked positions.

6.3 Preparation for Mounting on a Base

Requirements:
☐ Foundation pit and subgrade must be prepared for the installation of the base (see Technical Information "Installation
Requirements ‒ Important Information on Transportation and Installation for Sunny Central 500CP XT ⁄ 630CP XT ⁄
720CP XT ⁄ 760CP XT ⁄ 800CP XT ⁄ 850CP XT ⁄ 900CP XT").
☐ The base must be installed.
Procedure:
1. Lead the AC, DC and data cables through the opening into the base. Route the data cables separately from AC and
DC cables.
2. Seal the opening, e.g. with expanding foam. This will prevent animals from penetrating the Sunny Central.
3. Fill up the excavation pit and level off to ground level.