Verifying The Installation; Powering On And Starting The Ups - Huawei UPS5000-A-300K-FT Quick Manual

Hide thumbs Also See for UPS5000-A-300K-FT:
Table of Contents

Advertisement

4

Verifying the Installation

1. Check that there is no foreign matter
in the cabinet.
Positions to be checked
(1) Switches
(2) Mains input wiring
copper bars
(3) Battery input
wiring copper bars
(4) Output wiring
copper bars
(5) Bypass input wiring
copper bars
(6) Rear of modules
2. After verifying the installation, reinstall all
the covers.
3. (Remove the paper protective film from
the sealing putty.) After routing cables
and verifying cable connections, seal the
gap between cables and the cabinet using
sealing putty.
Paper
protective
film
5

Powering On and Starting the UPS

1. Before powering on the UPS, ensure that the UPS has passed all check items in the
Commissioning and Acceptance Report
2. Measure the voltage and frequency of the UPS upstream input switch. The line voltage
range is 138–485 V AC, and the frequency range is 40–70 Hz.
Sealing putty must be
used as a whole and
the gap can be sealed
only from the top.
Sealing putty
and Chapter 4.
9
4. Do not remove the dustproof cover
before power-on to prevent dust inside
the UPS.
Dustproof cover