ABB Terra 360 CE Operation And Installation Manual page 78

Table of Contents

Advertisement

Installation
Procedure
1. Tell the owner that the EVSE is ready for commissioning.
2. Make sure that the site is in accordance with these requirements:
3. Make sure that these data are available:
78
The EVSE is installed.
AC input power is available from the grid provider.
You are present during the commissioning, for assistance and to energize
the power to the EVSE on the power distribution board.
Internet access is available, through 2G/3G/4G or through a wired Ethernet
connection.
An EV must be available with a compatible connection. If the EVSE has more
than one connection type, an EV of each type must be available.
The site operator or owner is available to receive instructions from the
service engineer of the manufacturer.
Contact data of the contact person on site
Address of the EVSE
Site name
Exact location of the EVSE: longitude and latitude. If there are more EVSEs on
one location, make sure that the coordinates are slightly different (at least
0.0001 degree) so that the EVSEs are not at the same location on the map.
Specification of the external fuse at the power distribution board
Date that the installation is done
Special remarks, for example to decline the authorization for the service
engineer of the manufacturer to take photos
Photo of the surroundings of the EVSE
9AKK108467A6398-EN | 002