COMMISSIONING
14.4 TEST RUN / AIR PURGE
Test run is a working mode used when commissioning the installation. Some settings are made to let the installer an easy job. Air
purge function drives the pump in a way for evacuating air bubbles in the installation.
This menu shows the following test to be launched:
•
Unit Test Run
•
Air Purge
•
Screed Drying
•
Pump down procedure
After "Test Run", "Air Purge" or "Pump down procedure" option is selected, the YUTAKI user controller asks for the duration of the
test.