3.10 Electrical connections

NOTE
The Figure 62 shows an example of a standard wiring diagram. Please refer to the
specific wiring diagram of the version you are installing before proceeding with the
connections.
NOTE
The wires are marked with an identification number which is also shown on the wiring
diagram.
Connect the M8, M9, M10, and M11 fans (3, Figure 62) of the evaporators (depending on the
version).
Connect the BA cold room probe (9).
Connect the defrosting valve YS (6) - if supplied.
Connect the defrost termination thermostat FTS (8) - if supplied.
Connect the injection valve YI (5).
Connect the injection thermostat FTI (4) - if supplied.
Install the FSC fuse under key (7), as indicated in the paragraph 3.10.1.
Connect the red cable R to the FGS (1) battery protection fuse (positive pole)
Connect the other end of the FGS fuse to the battery positive pole.
Connect the black cable B (2) to the battery negative pole.
Connect the exhaust resistance ES (6), as indicated in paragraph 3.10.1- if present.
54
INSTALLATION MANUAL
Figure 61 - Battery protection fuse (positive pole)
Refrigeration unit
Series Zero Direct-Drive
Z200 | Z250 | Z350 | Z380
Z380 Multi
rev.01

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Z200Z250Z350Z380 z380 multi

Table of Contents