6. Test Run

(1) Turn the indoor unit selector switch to the "ON"
position. (Fig. 37)
(2) With the remote controller, start heating or cooling
operation.
(3) Turn the selector switch to "TEST RUN." (The indi-
cator lamp blinks during test run operation.)
(4) After the test run is completed, turn the selector
switch to "ON." Operation stops, and remote con-
troller control becomes possible.
If the OPERATION lamp only blinks or the outdoor
unit does not start approximately 5 minutes after the
start of the test run, perform self-diagnosis by switch-
ing to OFF. Follow the self-diagnosis procedure listed
on the right inside of the grille.
The combination of the 3 indicator lamps indicates
the condition of the system. (Fig. 38)

7. Installation Check Sheet

The strength of the installation location is sufficient
to support the A/C weight.
The indoor and outdoor units are installed level and
vertically.
The power and voltage are as specified.
Inter-unit cables are securely inserted into the
terminal block.
Inter-unit cables are securely fixed.
The power cord and inter-unit cables are not con-
nected anywhere along their paths.
The ground wire is securely connected.
Thermal insulation has been applied to the tubing
connections.
Drain connections are secure and water drains
properly.
Putty has been used to close the hole in the wall.
Remote controller signals are being positively
received.
Fig. 37