Download Print this page
Mercia Garden Products 03WES0808-V1 General Instructions Manual

Mercia Garden Products 03WES0808-V1 General Instructions Manual

8x8 summerhouse, t&g roof and floor, double doors, opening window

Advertisement

Quick Links

General Instructions
03WES0808-V1
8X8 SUMMERHOUSE, T&G ROOF AND FLOOR, DOUBLE DOORS, OPENING WINDOW
BEFORE YOU START PLEASE READ INSTRUCTIONS CAREFULLY
- Check the pack and make sure you have all the parts listed.
- When you are ready to start, make sure you have the right tools at hand (not supplied)
including a Phillips screwdriver, Stanley knife, wood saw, step ladder and drill with 2mm
bit.
- Ensure there is plenty of space and a clean dry area for assembly.
TIMBER
As with all natural materials, timber can be a ected during various weather conditions.
For the duration of heavy or extended periods of rain, swelling of the wood panels may
occur. Warping of the wood may also occur during excessive dry spells due to an interior
moisture loss. Unfortunately, these processes cannot be avoided but can be helped. It is
suggested that the outdoor building is sprayed with water during extended periods of
warm sunshine and sheltered as much as possible during rain or snow.
Our buildings are pre treated with a water based treatment**; this only helps to protect
the product during transit and for upto 3 months against mould. To validate your
guarantee and ensure longevity of the product, it is ESSENTIAL the building is treated
with a wood preserver within the rst three months of assembly and thereafter in
accordance with the manufactures recommendations. Care must be taken to ensure
the product is placed on a suitable base.
BUILDING A BASE
When thinking about where the building and base is going to be constructed:
Ensure that there will be access to all sides for maintenance work and annual
treatment.
Ensure the base is level and is built on rm ground, to prevent distortion. Refer to
diagrams for the base dimensions, The base should be slightly smaller than the external
measurement of the building, i.e. The cladding should overlap the base, creating a run
o for water. It is also recommended that the oor be at least 25mm above the
surrounding ground level to avoid ooding.
TYPES OF BASE
- Concrete 75mm laid on top of 75mm hard-core.
- Slabs laid on 50mm of sharp sand.
Whilst all products manufactured are made to the highest standards of Safety and in
the case of childrens products independently tested to EN71 level, we cannot accept
responsibility for your safety whilst erecting or using this product.
Refer to the instructions pages for you speci c product code
Please retain product label and instructions for future reference
x2
All building's should be
erected by two adults
For ease of assembly, you
MUST pilot drill all screw
holes and ensure all screw
heads are countersunk.
2mm Drill bit
**Protim Aquatan T5 (621)**
Your building has been treated with Aquatan.
Aquatan is a water-based concentrate which is diluted with water, the building as been treated by the correct
application of Aquatan solution and then allowed to dry.
Aquatan is a decorative nish to colour the wood, which is applied industrially to timber fence panels and
garden buildings.
Aquatan undiluted contains: boric acid, sodium hydroxide 32% solution, aqueos mixture of sodium dioctyl
sulphosuccinat and alcohols: 2, 4, 6-trichlorophenol.
For assistance please contact customer care on: 01636 880514
Mercia Garden Products Limited,
Sutton On Trent,
Newark,
Nottinghamshire,
NG23 6QN
www.merciagardenproducts.co.uk
Winter = High Moisture = Expansion
Summer = Low Moisture = Contraction
CAUTION
Every e ort has been made during the
manufacturing process to eliminate the
prospect of splinters on rough surfaces of the
timber. You are strongly advised to wear gloves
when working with or handling rough sawn
timber.

Advertisement

loading
Need help?

Need help?

Do you have a question about the 03WES0808-V1 and is the answer not in the manual?

Questions and answers

Summary of Contents for Mercia Garden Products 03WES0808-V1

  • Page 1 TYPES OF BASE For assistance please contact customer care on: 01636 880514 - Concrete 75mm laid on top of 75mm hard-core. Mercia Garden Products Limited, - Slabs laid on 50mm of sharp sand. Sutton On Trent, Whilst all products manufactured are made to the highest standards of Safety and in...
  • Page 2 03WES0808-V1 Please retain product label and instructions for future reference Fixing Kit Overall Dimensions: Length = 2818mm Width = 2830mm Height = 2252mm Veranda Support - 27x44x1685mm Qty 2 Base Dimensions: Length = 2508mm Width = 2413mm Fascia - 12x95x1549mm Qty 4...
  • Page 3: Pre-Assembly

    Please retain product label and instructions for future reference Step 1 Pre Assembly Remove transportation Fix a Thinge to the top and bottom of each blocks from the bottom door and a hinge in the middle and x to of each panel before the door gable using 30mm black screws.
  • Page 4 Please retain product label and instructions for future reference Step 4 Step 2 Place the floor on a firm and Fix the door beading level base, ensure base has strips to the door gable suitable drainage free from using 4x40mm screws areas where standing water can for each strip.
  • Page 5 Please retain product label and instructions for future reference Step 6 Step 8 Fix the corners with 50mm Once the roof is fixed attach screws as shown in diagram. the building to the floor with 50 mm screws ensuring that 9x50mm Screws the screws go through to the floor bearers.
  • Page 6 Please retain product label and instructions for future reference Step 12 Step 10 Secure the Veranda rails to the Cut the felt into 3 sheets at 2900mm and fix outside edge of the veranda onto the roof using felt tacks as shown in floor and to the building.
  • Page 7 Please retain product label and instructions for future reference Step 13 Step 14 Fit the fascias to the roof over the felt and secure in place with 40mm screws as 30mm shown. ensuring the screws screw go through into the roof Place the opening window strip framing Attach the finial to 11mm above the window gap in the...
  • Page 8 Please retain product label and instructions for future reference Step 15 Step 16 Pre drill hole Fix the casement stay to the Attach the Tower Bolt Strip to 30mm opening window then align screw top and bottom of the slave door the fixings onto the window with 2x30mm screws.
  • Page 9 Please retain product label and instructions for future reference Step 19 Attach a turn button to the top and bottom of the slave door using 30mm black screws ensur- ing once turned horizontal the turn button catches the master door. These turn buttons help to keep your doors straight during high levels and...