Fujitsu AUXG07KVLA Manual page 225

2-unit multi-split type
Hide thumbs Also See for AUXG07KVLA:
Table of Contents

Advertisement

Check point 3. Check the wired remote controller and controller PCB
[Compact cassette and floor types]
Check voltage at CN14 (terminal 1—3, terminal 1—2) of main PCB.
(Power supply to remote controller)
If it is DC 12 V, the remote controller is failure. (The controller PCB is normal)
-> Replace the remote controller.
If it is DC 0 V, the controller PCB is failure. (Check the remote controller once
again)
-> Replace the controller PCB.
[Wall mount type for KGTB, KGTE, KMCE, KETA, KETE]
Check voltage at CN300 (terminal 1—2) of main PCB or communication PCB.
(Power supply to remote controller)
If it is DC 12 V, the remote controller is failure. (The controller PCB is normal)
-> Replace the remote controller.
If it is DC 0 V, the controller PCB is failure. (Check the remote controller once
again)
-> Replace the controller PCB.
[Wall mount type for KMTB, KMCC]
Check voltage at CNC01 (terminal 1—3) of main PCB or communication PCB.
(Power supply to remote controller)
If it is DC 13 V, the remote controller is failure. (The controller PCB is normal)
-> Replace the remote controller.
If it is DC 0 V, the controller PCB is failure. (Check the remote controller once
again)
-> Replace the controller PCB.
[Mini duct and Slim duct types]
Check voltage at CN300 (terminal 1—3, terminal 1—2) of main PCB.
(Power supply to remote controller)
If it is DC 12 V, the remote controller is failure. (The controller PCB is normal)
-> Replace the remote controller.
If it is DC 0 V, the controller PCB is failure. (Check the remote controller once
again)
-> Replace the controller PCB.
Check point 4. Replace the main PCB
If check point 1 to 3 do not improve the symptom, replace the main PCB.
3-3. No operation (Power is on)
End
- (03-61) -
3. Troubleshooting without error code