Operation Manual / Power2 340-H / Low-pressure stage
3 Removal and installation / 3.3 Installing the low-pressure stage
3.3.3
Steps for fastening the low-pressure stage
Fig. 15: Low-pressure stage, tightening the fixing screws.
Tighten the fitted fixing screws (01) according to the following table:
u
Power2
340 LP
Table 9: Fixing screw tightening torque (01)
If a support is present, tighten the fixing screws (05) according to the following table:
u
Power2
340 LP
Table 10: Fixing screw tightening torque (05)
Then tighten the hexagon-head screw (61003).
u
Power2
Hexagon-head screws (61003) [mm]
340 LP
Table 11: Tightening torque (61003)
Remove lifting gear.
u
Connect the cable connector (86515) to the speed sensor (86505)
u
low-pressure stage on the bracket
Connect all gas pipes and air lines.
u
Version with water-cooled bearing casing
Fit the water pipes according to the instructions of the enginebuilder.
u
© Copyright 2022 ABB. All rights reserved.
Fixing screws (01) [mm]
M20
Fixing screws (05) [mm]
M16
M20
→34).
HZTL4053_EN
Tightening torques [Nm] (friction
coefficient µ=0.12)
455
Tightening torques [Nm]
180
Tightening torques [Nm]
320
(see Fig. 14: Placing the
Rev.F
March 2022