Knockdown steel adjustable-height gantry cranes

Advertisement

Step 4: Fasten I-beam to uprights.
[NOTE: Shim only used with models AHSN-6-20-12, 6-20-14, 6-20-16, 8-20-12, 8-20-14 & 8-2016.]
a. Insert the flange of the I-beam into the gap between the beam clamp and the top of the uprights (see FIG. 4B
below);
b. Then clamp the flange on the opposite side of the beam to the beam bracket with the remaining beam clamps
as shown in the diagram below.
FIG. 4B: Clamp the I-beam to the tops of the uprights
Beam clamp
I-beam
Flange of I-
beam
FIG. 4C: Beam-to-upright connection
Beam
flange
Step 5: Tighten the beam clamp nuts and bolts to 50 - 52 ft·lb of torque.
Step 6: Put the crane on its feet.
Rotate the crane onto its feet in a controlled manner. For instance, attach a hoist chain to the I-beam and slowly
raise the beam until the crane stands on its feet. Alternatively, raise the crane with a fork truck. Position the forks
under the I-beam and slowly raise the beam until the crane rotates onto its feet in a controlled manner.
Approach the crane with
a fork truck from this side
and slide the forks under
the I-beam.
Slowly raise the beam
and drive forward until
the crane stands on its
feet.
Rev. 1/4/2017
Shim
Upright
Beam
clamp
Copyright 2017 Vestil Manufacturing Corp.
FIG. 4A: End View of I-beam
Connection to Beam Bracket
FIG. 4D: Beam-to-upright connection including shim
Fig. 3D:
Top view of beam connection to
upright
Beam flange
Shim
Page 20 of 26
AHSN, MANUAL.doc
Beam
clamp