4
Testing Procedures
To make sure that all components have been installed correctly, perform the following testing
procedures. You will need (Fig. 4):
A T-joint
A valve
A pressure gauge (min. 4-BAR)
A 12-Volt power supply
CNG joints
Hoses, to connect the components
1. Connect the regulator/vaporizer to a compressed air circuit.
Fig. 4.1
ZAVOLI s.r.l. Via Pitagora n° 400 47023 Fr. Case Castagnoli, CESENA (FC), Italy
Technical Directions
for the Overhaul of
GE – GES – GEX – GEXL
Regulators/Vaporizers
Fig. 4
Page 28 of 32