Items Not Supplied
The following items are NOT supplied with the unit:
Compressed nitrogen @ 96.5 bar (1,400 psi)
•
External safety device on the feed supply or product discharge lines
•
Site Preparation
NOTE: Check the shipping container and its contents for damage. If damage is suspected, notify
both the carrier and MFIC immediately on the straight bill of lading (supplied by the
carrier). If any damage is found, you may request an inspection by the carrier. Such
requests should be made as quickly as possible.
Compare the contents of the packing list against the contents of the shipping container to
•
ensure receipt of all components.
Locate the desired operating site and prepare sufficient space for the equipment (refer to
•
Figure 3.1).
Ensure that the proposed operating site meets all the environmental specifications listed
•
in this chapter (refer to the Environmental Requirements section).
Make available sufficient electric power. Then, connect to the system (refer to the Utility
•
Requirements section).
NOTE: We recommend saving the shipping container for possible future use (i.e., in case you need
to return the equipment for service).
Figure 3.1 Site Plan Clearance
3-LV-1-7 9/7/11
Chapter 3: Operation
LV1 User Manual
3-3
Need help?
Do you have a question about the MICROFLUIDIZER LV1 Series and is the answer not in the manual?