INSTALLATION AND INITIAL TURN-ON
Power Tracker Fine Tuning:
• All PV-100208 operating parameters have been set at the factory, based upon prior experience with
PV arrays.
• It is recommended that the PV-100208 be watched during Wake-Up and Sleep Test. If the PV-
100208 cycles between operating and sleeping at either of these times, the condition setpoints are
not set properly (refer to section 4 for detailed description of PV-100208 state transitions). The
PV100208 should not cycle if the setpoints are set properly.
Some field adjustable parameters are password protected and may only be changed
by trained service technicians. In particular are parameters relating to utility
protection setpoints. These have been set in the factory to the limits mandated by
UL1741. Any changes to these setpoints should be agreed upon by the local utility
and the equipment owner.
Visually inspect the exterior surfaces for any damage (nicks, chips, exposed base
metal and scratches) that may have occurred during shipment or installation.
Touch up or recoat using White NISSEN Feltip Paint Marker, or equivalent to
prevent rust or corrosion.
DOCUMENT: 151700
NOTE
NOTE
PV-100208 Photovoltaic Inverter
Operation and Maintenance Manual
Copyright 2003, Xantrex Technology Inc.
3-8

Advertisement

Table of Contents
loading

Table of Contents