Xantrex PV100S-480 Planning And Installation Manual
Xantrex PV100S-480 Planning And Installation Manual

Xantrex PV100S-480 Planning And Installation Manual

100 kw grid-tied photovoltaic inverter
Hide thumbs Also See for PV100S-480:
Table of Contents

Advertisement

PV100S 100 kW
Grid-Tied
Photovoltaic
Inverter
PV100S-208
PV100S-480
Planning and Installation Manual

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PV100S-480 and is the answer not in the manual?

Questions and answers

Summary of Contents for Xantrex PV100S-480

  • Page 1 PV100S 100 kW Grid-Tied Photovoltaic Inverter PV100S-208 PV100S-480 Planning and Installation Manual...
  • Page 3 PV100S 100 kW Grid-Tied Photovoltaic Inverter Planning and Installation Manual...
  • Page 4 About Xantrex Xantrex Technology Inc. is a world-leading supplier of advanced power electronics and controls with products from 50 watt mobile units to 1.5 MW utility-scale systems for wind, solar, batteries, fuel cells, microturbines, and backup power applications in both grid-connected and stand-alone systems. Xantrex products include inverters, battery chargers, programmable power supplies, and variable speed drives that convert, supply, control, clean, and distribute electrical power.
  • Page 5: About This Manual

    About This Manual Purpose The purpose of this Planning and Installation Manual is to provide explanations and procedures for planning and installing the PV100S 100 kW Grid-Tied Photovoltaic Inverter. Scope The Manual provides safety guidelines, detailed planning and setup information, and procedures for installing the inverter.
  • Page 6: Conventions Used

    • The model PV100S-480 100kW Grid-Tied Photovoltaic Inverter (480 Vac input) will be referred to as the PV100S-480 when it is being referenced individually. • When the both models are being referenced together, they will be referred to as the PV100S.
  • Page 7: Abbreviations And Acronyms

    IGBT kcmil NFPA POTS UFCU Related Information You can find more information about Xantrex Technology Inc. as well as its products and services at www.xantrex.com. 152315 Rev C American National Standards Institute Converter Control Unit 2 Cubic Feet per Minute...
  • Page 9: Important Safety Instructions

    Important Safety Instructions SAVE THESE INSTRUCTIONS - DO NOT DISCARD This manual contains important safety instructions for the PV100S that shall be followed during installation and maintenance procedures. WARNING: Shock Hazard Read and keep this Planning and Installation Manual for future reference. Before installing PV100S (either model), read all instructions, cautionary markings, and all other appropriate sections of this manual.
  • Page 10: General Safety Precautions

    4. The AC power conductor wiring interfacing with the AC terminals in the Transformer Enclosure are located at T6-X1, T6-X2, and T6-X3. These terminals should be tightened to a torque value of 420 in-lbs (47.5 Nm) for model PV100S-208 and model PV100S-480. Conductors terminated to these viii 152315 Rev C...
  • Page 11 310 in-lbs (35.0 Nm) for model PV100S-208 and to a torque value of 115 in-lbs (13.0 Nm) for model PV100S-480. See Figure 3-16 on page 3–16 for the location of these terminals and the cautionary note on page 3–17.
  • Page 12: Lockout And Tag

    Safety Operational Safety Procedures Never work alone when servicing this equipment. A team of two is required until the equipment is properly de-energized, locked-out and tagged, and verified de- energized with a meter. Thoroughly inspect the equipment prior to energizing. Verify that no tools or equipment have inadvertently been left behind.
  • Page 13: Interconnection Standards Compliance

    De-Energize/Isolation Procedure The following procedure should be followed to de-energize the PV100S for maintenance. WARNING The terminals of the DC input may be energized if the PV arrays are energized. In addition, allow 5 minutes for all capacitors within the main enclosure to discharge after disconnecting the PV100S from AC and DC sources.
  • Page 15: Table Of Contents

    Contents Important Safety Instructions 1 Introduction Description of the PV100S - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1–2 System Specifications - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1–4 Electrical Specifications - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1–4 Over Voltage, Under Voltage and Frequency Ranges - - - - - - - - - - - - - - - - - - - - - - - - - 1–4...
  • Page 16 Contents 3 Installation Equipment Required - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3–2 Unloading - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3–2 Moving the PV100S - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3–3 Unpacking the PV100S - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 3–3...
  • Page 17 Tables Table 1-1 Electrical Specifications - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1–4 Table 1-2 Over/Under Voltage and Over/Under Frequency Ranges - - - - - - - - - - - - - - - - - - - - - - 1–4 Table 1-3...
  • Page 19 Figures Figure 1-1 Dimensions (Not to scale) - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1–3 Figure 1-2 PV100S Operator Interface Components- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1–7 Figure 1-3...
  • Page 20 PV100S-480 Schematic for Control Power Distribution (152316 E2) - - - - - - - - - - - - - A–5 Figure A-4 PV100S-480 Schematic for Converter Control Unit (152316 E3)- - - - - - - - - - - - - - - - A–6 Figure A-5 PV100S-208 Schematic Main Power Distribution (152376 C1) - - - - - - - - - - - - - - - - - A–7...
  • Page 21: Introduction

    Introduction Chapter 1, “Introduction” provides information about the features and functions of the PV100S 100 kW Grid-Tied Photovoltaic Inverter.
  • Page 22: Description Of The Pv100S

    Introduction Description of the PV100S The PV100S 100 kW Grid-Tied Photovoltaic Inverter is a UL 1741 listed, utility interactive, three-phase power conversion system for grid-connected photovoltaic arrays with a power rating of 100 kW. Designed to be easy to install and operate, the PV100S automates start-up, shutdown, and fault detection scenarios.
  • Page 23: Figure 1-1 Dimensions (Not To Scale)

    Front View Communications Enclosure 49 7/8" (124.8 cm) Interface Enclosure Transformer 44.0" (110 cm) 21 3/8" (53.5 cm) Back AC Interface Enclosure DISCONNECT 33 ½" (83.75 cm) AC Side View Figure 1-1 Dimensions (Not to scale) 152315 Rev C TH I S U N I T EM P L O Y S FI E L D A D JU S T AB LE V O LT A G E A N D FR E Q U E N C Y S E T POI N T S A N D T I M E D E L AY S.
  • Page 24: System Specifications

    528 < Vac < 657 2 cycles 657 < Vac 6 cycles f < 59.3 6 cycles f > 60.5 PV100S-480 480 Vac (422 to 528 Vac) 121 A 60 Hz (59.3 to 60.5 Hz) 100.0 kW 330 to 600 Vdc...
  • Page 25: System Ground Requirements

    System Ground Requirements This product is intended to be installed as part of a permanently grounded electrical system per the National Electric Code ANSI/NFPA 70. A copper ground rod must be installed within three feet of the PV100S enclosures and connected to the unit as described in “System Grounding”...
  • Page 26: Environmental Specifications

    Introduction Environmental Specifications The following environmental specifications are the same for both models of the PV100S 100 kW Grid-Tied Photovoltaic Inverter. Table 1-3 Environmental Specifications Specification Dimensions Inverter and DC Interface Transformer and AC Interface Overall System Footprint: Weight Inverter and DC Interface Transformer and AC Interface Overall Weight Allowable Ambient Temperature...
  • Page 27: Operator Interface Controls

    Operator Interface Controls Operator interface controls are located on the front door of the main inverter enclosure. These controls include an ON/OFF Switch, 4-line LCD display and keypad called the Universal Frontpanel Control Unit (UFCU). Additionally there is an AC and DC Disconnect on the AC Interface Enclosure and the DC Interface Enclosure Doors.
  • Page 28: On/Off Switch

    Introduction WARNING: Shock Hazard Disengaging the main enclosure door interlock switch does NOT remove all hazardous voltages from inside the inverter. Before attempting to service the PV100S, follow the de-energize Lockout and Tag procedure on page x. On/Off Switch The PV100S incorporates a maintained position front door of the main enclosure.
  • Page 29: Ac And Dc Disconnect Switches

    AC and DC Disconnect Switches Both AC and DC Interface Enclosures are equipped with lockout hasps for personnel safety. The enclosure doors should not be opened while the PV100S is operating. The switch handles and shafts provide a door interlock for both the AC and DC interface enclosures.
  • Page 30: System Status And Fault Reporting

    Introduction System Status and Fault Reporting Basic system status and all fault conditions rising from within the PV100S are reported to the UFCU. The unit stores the time and details of all faults in non-volatile memory. The 4-line LCD will display a hexadecimal value and a brief text description of the fault.
  • Page 31: Communication Methods

    Communication Methods The PV100S communicates system status information to the user using the following methods. • The Front Panel Control Unit (UFCU) Display • PC Connection (Direct or Remote) - Xantrex Solar Graphic User Interface (GUI) Software required. Communication with a PC requires the selection of one of the following options.
  • Page 32: Pc Connection Methods

    Introduction PC Connection Methods Personal computers can be used to access the system status and programming features of the PV100S. A computer can be connected either directly or remotely. 1. Remote Connect - uses one of the three kits below. •...
  • Page 33: Pots Access

    POTS Access Figure 1-7 illustrates the PV100S connected remotely to a personal computer. Figure 1-7 POTS Access Wireless Access Figure 1-8 illustrates the PV100S connected remotely to a personal computer using a wireless network. Figure 1-8 Wireless Access 152315 Rev C Communication Methods 1–13...
  • Page 34: Ethernet Lan Access

    Introduction Ethernet LAN Access The PV100S can be remotely accessed through a local area network. Figure 1-9 Ethernet LAN Access Direct Access Figure 1-10 illustrates the PV100S connected directly to a personal computer. Figure 1-10 Direct Access 1–14 152315 Rev C...
  • Page 35: Planning

    Planning Chapter 2, “Planning” provides information to help plan the installation of the PV100S 100 kW Grid-Tied Photovoltaic Inverter.
  • Page 36: Overview Of Pv100S Installation

    Planning Overview of PV100S Installation WARNING: Shock Hazard Installations of this equipment should only be performed by qualified technicians. Installers must meet all local and state code requirements for licensing and training for the installation of Electrical Power Systems with AC and DC voltage to 600 volts.
  • Page 37: Pv Planning

    Large gauge wire must conform to the minimum bend radius specified in the NEC, Article 373-6B, Ninth Edition. Take care to keep the wire bundles away from any sharp edges which may damage wire insulation over time. All conductors should be made of copper and rated for 90 °C (minimum). If the installation of the PV100S is to be outdoors, all interconnect conduit and fittings must be NEMA 4 rated as required by the NEC.
  • Page 38: Ground Requirements

    Planning Ground Requirements This product is intended to be installed as part of a permanently grounded electrical system per National Electric Code ANSI/NFPA 70. A copper ground rod must be installed within three feet of the PV100S enclosure. This is the single point earth ground for the inverter system.
  • Page 39: Electrical Diagrams And Schematics

    For more detailed information, refer to the schematic illustrations for model-specific electrical schematics. Model PV100S-480: • Figure A-2, “PV100S-480 Schematic for Main Power Distribution (152316 E1)” on page A–4 • Figure A-3, “PV100S-480 Schematic for Control Power Distribution (152316 E2)” on page A–5 •...
  • Page 40: Layout Options

    Planning Layout Options The PV100S is shipped as two separate assemblies and can be arranged as shown in Figure 2-1 or Figure 2-2. The PV100S can be arranged in a number of different system layout options to fit specific site requirements. The AC interface/transformer assembly may be co-located adjacent to the left side of (or behind) the Main Inverter Enclosure up to, and not exceeding, 15 feet away.
  • Page 41: Figure 2-2 Pv100S Layout Option B

    Minimum Dimension of Base: Approximately 9 ft by 7 ft (2.7 m x 2.1 m) 12" Minimum Clearance Conduit (not to exceed 15') Communications 12" Minimum Clearance Figure 2-2 PV100S Layout Option B 152315 Rev C BASE: Concrete Floor or Pad 36"...
  • Page 42: Conduit Penetration

    Planning Conduit Penetration The following illustrations show the recommended locations for electrical conduit entry into the PV100S enclosures. These drawings are to be used for system planning purposes, such that the shaded areas are representative of the maximum allowable area and location in which electrical conduit may penetrate the enclosures of the PV100S, see Figure 2-3 through Figure 2-8.
  • Page 43: Figure 2-4 Inductor Enclosure Conduit Entry, Left Side

    Figure 2-4 Inductor Enclosure Conduit Entry, Left Side 12" (30 cm) 12" 6" (15 cm) 6" Figure 2-5 Transformer Enclosure Conduit Entry, Right Side 152315 Rev C 6" 6" (15 cm) 2" 2" (5 cm) 12" 12" (30 cm) 6" (15 cm) 6"...
  • Page 44: Figure 2-6 Ac Interface Enclosure Conduit Entry, Left Side

    Planning Backside of Transformer Enclosure (partial view) Figure 2-6 AC Interface Enclosure Conduit Entry, Left Side Figure 2-7 DC Interface Enclosure, Bottom Side 1" (2.5 cm) 10 ½" 10.5" (27 cm) Figure 2-8 Communications Enclosure Conduit Entry, Bottom Side 2–10 8"...
  • Page 45: Conductor And Conduit Sizing

    Conductor and Conduit Sizing All wiring methods and materials shall be in accordance with the National Electrical Code ANSI/NFPA 70. When sizing conductors and conduits interfacing to the PV100S, both shall be in accordance with the National Electric Code ANSI/NFPA 70, as well as all state and local code requirements. Large gauge wire must conform to the minimum bend radius dependent upon the wire gauge (refer to the National Electric Code, Article 373-6B (Ninth Edition).
  • Page 46 Planning Step 3. Size the cable. This example assumes that the conduit length is less than 24 inches. NEC Table 310.16 (Ninth Edition) indicates the Temperature Correction Factor for 90 °C THHN cable in a 50 °C ambient is 0.82. With a required ampacity from Step 1 above of 347 amps, it can be calculated that the required cable ampacity at 50 °C in this application is 423 amps.
  • Page 47: Anchoring The Pv100S

    Anchoring the PV100S The PV100S is designed to be installed in either an indoor or outdoor location. It must be placed on and anchored to a level concrete floor or pad. The concrete floor or pad, upon which the PV100S is anchored, must be structurally designed to meet any local, state, or national requirements for weight, seismic, and wind sheer if applicable.
  • Page 48: Figure 2-10 Ac Interface/Transformer Anchor Bolt Pattern (Not To Scale)

    Planning 17 ½" (44 cm) 25" (63.5 cm) Figure 2-10 AC Interface/Transformer Anchor Bolt Pattern (Not to Scale) The floor or pad should either be pre-drilled to accept masonry anchors or have pre-installed anchoring bolts. 2–14 29" (73.7 cm) ¾" (1.9 cm) (x6) 152315 Rev C...
  • Page 49: Installation

    Installation Chapter 3, “Installation” describes the procedures needed to install the PV100S 100 kW Grid-Tied Photovoltaic Inverter. This section includes unpacking and moving instructions, mounting instructions, and cabling instructions.
  • Page 50: Equipment Required

    Installation Equipment Required The following is a list of required tools and equipment to aid in the installation of the PV100S. This list is not a comprehensive list, but is intended to help identify the minimum recommended tools and equipment used during the installation. •...
  • Page 51: Moving The Pv100S

    Moving the PV100S CAUTION: Equipment Damage To move the PV100S, use a forklift that has a sufficient lift capacity and has a 26" fork span. To move the PV100S while it is still inside the shipping crates: 1. Place the forks of the forklift below the shipping crate at the points specified on the shipping crate.
  • Page 52: Removing The Pallet And Moving The Pv100S

    Installation Removing the Pallet and Moving the PV100S CAUTION: Equipment Damage To move the PV100S, use a forklift that has a sufficient lift capacity and a 26" fork span. To move the PV100S using a forklift: 1. Place the forks of the forklift below the unit at the points specified in Figure 3-2.
  • Page 53: Mounting And Anchoring The Units

    Important: of the components, conduit penetration locations, conductor and conduit sizing, and method for anchoring the unit. Ensure adequate space is provided for clearance for ventilation and serviceability. Review Chapter 2, “Planning” if necessary before proceeding. Mounting and Anchoring the Units To mount and anchor the PV100S: 1.
  • Page 54: Opening Or Closing Access Doors

    Installation Opening or Closing Access Doors To lock or unlock the front door on the main inverter: 1. Use the 7 mm triangle key provided with the unit. a) Insert the key in the lock and turn counterclockwise to open; b) Pull front door open from the right side.
  • Page 55: Figure 3-5 Ac Interface Access Door

    Figure 3-5 AC Interface Access Door Figure 3-6 DC Interface Access Door 152315 Rev C To Open Access Door: 1. Confirm that the AC Disconnect Switch handle is placed in the OFF (Open) position prior to opening the door. 2. Loosen the bolts on door latches and slide away from the door.
  • Page 56: Figure 3-7 Transformer Access Panels

    Installation Figure 3-7 Transformer Access Panels Figure 3-8 Inductor Access Panels 3–8 Transformer Access Panel To Remove the Access Panel: Loosen and remove the 1/4" self-tapping sheet metal screws (x6). To Replace the Access Panel: Replace and tighten the 1/4" self-tapping sheet metal screws.
  • Page 57: Conduit Installation

    Conduit Installation Given the flexible nature of the system, conduit installation will be dependent upon the final configuration of the system. Procurement and installation of the conduit, therefore, is the responsibility of the installer. Since the layout will be dependent upon the location available for the installation and the size of the conductors used, specific conduit size and type must be pre-determined by the installer before the actual installation.
  • Page 58: Wiring - General

    Installation Wiring - General All wiring methods and materials shall be in accordance with the National Electrical Code ANSI/NFPA 70. When sizing conductors and conduits interfacing to the PV100S, both shall be in accordance with the National Electric Code ANSI/NFPA 70, as well as all state and local code requirements. WARNING: Shock Hazard The PV100S enclosures contain exposed high-voltage conductors.
  • Page 59: Overcurrent Protection

    • 400A maximum for PV100S-208 • 200A maximum for PV100S-480 Conductor Termination The PV100S has terminals and bus bars for making all wiring connections required for the installation. All terminals used for making AC and DC connections require the use of copper conductors with an insulation rating of 90 °C (or higher).
  • Page 60: Wire Gauge And Torque Requirements

    National Electric Code ANSI/NFPA 70. The single-point ground for the system is to be made at the AC ground bar (TB2) in the AC Interface Enclosure. AC Interface Enclosure Figure 3-10 Single-point Ground (TB2) Ground Bar 3–12 Bolt (Hardware) Size PV100S-208 PV100S-480 3/8-16 3/8-16 3/8-16 3/8-16 3/8-16 3/8-16...
  • Page 61: System Neutral Requirements

    Torque connections to ground bar in the Main Inverter Enclosure as follows: • PV100S-208 - 420 in-lbs (47.5 Nm) • PV100S-480 - 420 in-lbs (47.5 Nm) The equipment ground on the PV100S is marked with this symbol: AC Ground Bar (TB1) to be used...
  • Page 62: Wiring - Specific

    Installation inter-tie. The PV100S is a balanced, three-phase, current-sourcing inverter and only operates with the presence of a stable utility voltage. The transformer is also supplied with a neutral connection on the utility interconnect. Connection of this utility-side neutral does not affect the operation of the inverter, however connection of the neutral on the inverter-side does affect the operation and must be left floating or disconnected.
  • Page 63: Figure 3-13 Tie-Wraps On The Ac Sense Harness

    3. In addition to the power conductors, route the AC Sense Harness assembly (Xantrex P/N 1-152403-01) between the main inverter to the AC interface/transformer assembly. Prior to completing the installation of the AC Sense Harness, secure the harness to the AC power conductors with nylon tie-wraps so it does not touch the surfaces of the L1 inductor.
  • Page 64: Figure 3-15 Ac Terminal Connections In The Main Inverter Enclosure

    Installation 5. Connect the AC power conductors in the Main Inverter Enclosure at TB4-A (A phase), TB4-B (B phase), and TB4-C (C phase) with a box connector using a 5/16" Hex screw. This hardware should be tightened to a torque value of 275 in-lb (31 Nm).
  • Page 65: Figure 3-17 Connecting The Ac Sense Harness

    M10 (PV100S-208) hardware. Cables to these terminals must use a crimp-on type ring terminal or compression-type lug. Torque these connections to 115 in-lbs (13.0 Nm) for the M8 (PV100S-480), and 310 in-lbs (35.0 Nm) for the M10 (PV100S-208). See Figure 3-18 for the location of these terminals.
  • Page 66: Figure 3-18 Ac Terminal Connections From The Utility

    228 in-lbs (25.7 Nm) for TB6, and 420 in-lbs (47.5 Nm) for TB2 for both the PV100S-480 and PV100S-208 systems. See Figure 3-18 for the location of these terminals.
  • Page 67: Pv Array Connections

    DC Interface enclosure at the TB3 locations are made with box connector using a 7/16" Hex Allen screw. The hardware should be tightened to a torque value of 500 in-lbs. (56.5 Nm) for both the PV100S-480 and PV100S-208 systems. 5. Close the door to the DC Interface Enclosure and replace the door clamps.
  • Page 68: Pc Communications

    Installation PC Communications Personal computers can be used to access the system status and programming features of the PV100S. A computer can be connected either directly or remotely. 1. Remote Connect - uses one of the three kits below. • •...
  • Page 69: Establishing A Pots Connection

    Establishing a POTS Connection Important: feature. The phone line used for PV100S communication cannot be routed through a Private Branch Exchange (PBX) unless an analog PBX card is used. To connect a personal computer using the POTS Connection: 1. Ensure the personal computer to be used has a 56K modem installed. 2.
  • Page 70: Establishing Wireless Connection

    Installation Establishing Wireless Connection Important: provider before proceeding. To connect a personal computer using the GSM Wireless modem: 1. Ensure the personal computer has the appropriate hardware installed to support this feature. 2. Install the GUI Software following the instructions in the PV100S 100 kW Grid-tied Photovoltaic Inverter Operation and Maintenance Manual.
  • Page 71: Direct Connection

    Direct Connection The direct connection provides the means to use the features of the GUI by connecting a PC directly to the CCU2. This allows field personnel to monitor and control the inverter from a nearby laptop computer directly connected by a serial cable.
  • Page 72: Figure 3-22 Direct Connect Installation

    Installation Figure 3-22 Direct Connect Installation 3–24 RE232/FO Converter DB25-to-DB25 Gender Changer Adapter DB25/DB9 Serial Cable 152315 Rev C...
  • Page 73: Verification

    Verification Chapter 4, “Verification” provides a checklist to ensure the installation of the PV100S is correct and complete.
  • Page 74: Verification Procedure Summary

    Verification Verification Procedure Summary WARNING: Electrocution Hazard This chapter describes specific steps to ensure the installation of the PV100S 100 kW Grid-Tied Photovoltaic Inverter is correct and complete. Failure to adhere to these warnings could result in severe shock or possible death. Exercise extreme caution at all times to prevent accidents.
  • Page 75: Visual Inspection Of Mechanical Connections

    Visual Inspection of Mechanical Connections To perform a visual inspection of the PV100S mechanical connections: 1. Ensure that the AC and DC Disconnect Switches, as well as any utility interconnect circuit breakers or main disconnect switches, are opened. 2. Ensure all anchor bolts and any required seismic bracing is properly tightened and in place.
  • Page 76: Visual Inspection, Isolation Transformer Wye/Wye

    Verification Visual Inspection, Isolation Transformer Wye/Wye To perform a visual inspection of the Isolation Transformer Wye/Wye: 1. Ensure that the AC and DC Disconnect Switches, as well as any utility Interconnect circuit breakers or main disconnect switches, are open. 2. Verify all conductor and wiring connections interfacing with the PV100S are tightened to the correct torque value.
  • Page 77: A Schematics

    Schematics Appendix A contains useful schematics to aid with installation.
  • Page 78 Schematics This page intentionally left blank. A–2 152315 Rev C...
  • Page 79: Figure A-1 Electrical Diagram (Sample

    Appendix A Schematics Figure A-1 Electrical Diagram (sample) 152315 Rev C...
  • Page 80 Schematics Appendix A Figure A-2 PV100S-480 Schematic for Main Power Distribution (152316 E1) 152315 Rev C...
  • Page 81 Appendix A Schematics Figure A-3 PV100S-480 Schematic for Control Power Distribution (152316 E2) 152315 Rev C...
  • Page 82 Schematics Appendix A Figure A-4 PV100S-480 Schematic for Converter Control Unit (152316 E3) 152315 Rev C...
  • Page 83 Appendix A Schematics Figure A-5 PV100S-208 Schematic Main Power Distribution (152376 C1) 152315 Rev C...
  • Page 84 Schematics Appendix A Figure A-6 PV100S-208 Schematic for Control Power Distribution (152376 C2) 152315 Rev C...
  • Page 85 Appendix A Schematics Figure A-7 PV100S-208 Schematic for Converter Control Unit (152376 C3) 152315 Rev C...
  • Page 86 Schematics Appendix A This page was intentionally left blank. A-10 152315 Rev C...
  • Page 87: Index

    Index Abbreviations and Acronyms 3 – 6 Access Doors 2 – 13 Anchoring 3 – 13 Array Grounding CCU2 3 – 13 Chassis Grounds 2 – 2 Clearance 2 – 4 Communication 3 – 20 Communications 2 – 2 Components 2 –...
  • Page 88 Index 3 – 4 Removing the Pallet Safety Torque and Wire Gauge Specifications UFCU 3 – 2 Unloading 3 – 3 Unpacking Utility Side Isolation Transformer Requirements Verification Procedure Summary Visual Inspection of Electrical Connections Visual Inspection of Mechanical Connections Visual Inspection, Isolation Transformer Wye/Wye 4 –...
  • Page 90 Xantrex Technology Inc. 1 800 670 0707 Tel toll free NA 1 360 925 5097 Tel direct 1 360 925 5143 Fax direct customerservice@xantrex.com www.xantrex.com 152315 Rev C Printed in USA...

This manual is also suitable for:

Pv100s-208

Table of Contents