WARNING
The installation of this product must be carried out
only by authorised personnel to the requirements of
Australian Standard AS 5601, local authority, gas, elec-
tricity and any other relevant statutory regulation.

Advertisement

loading
Need help?

Need help?

Do you have a question about the Murelle Green Planet 110 HE I and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Sime Murelle Green Planet 110 HE I

  • Page 1 Murelle Green Planet 110 HE I/E Installation, User and Service Instructions WARNING The installation of this product must be carried out only by authorised personnel to the requirements of Australian Standard AS 5601, local authority, gas, elec- tricity and any other relevant statutory regulation.
  • Page 2 SAFE HANDLING This boiler may require 2 or more operatives to move it into its installation site, remove it from its packaging and during movement into its installation location. Manoeuvring the boiler may include the use of a sack truck and involve lifting pushing and pulling.
  • Page 3: Table Of Contents

    FONDERIE SIME S.p.A. of Via Garbo 27 - Legnago (VR) - Italy declares that its hot water boilers, which bear the CE mark under Gas Directive 90/396/CEE and are fitted with a safety thermostat calibrated to a maximum of 110°C, are not subject to application of PED Directive 97/23/CEE as they meet the requirements of article...
  • Page 4: Description Of The Boiler

    (from 20% to 100%). an Directives 2009/142/CE, 2004/108/CE, DIMENSIONS 1.2.1 MURELLE GREEN PLANET 110 HE I (fig. 1) FIXTURES Heating return G 1 1/2” (UNI - ISO 228/1) R3 D.H.W. tank return G 1 1/2”...
  • Page 5 1.2.2 MURELLE GREEN PLANET 110 HE E (fig. 1/a) FIXTURES Heating return G 1 1/2” (UNI - ISO 228/1) R3 D.H.W. tank return G 1 1/2” (UNI - ISO 228/1) Heating flow G 1 1/2” (UNI - ISO 228/1) Gas connection G 3/4”...
  • Page 6 TECHNICAL FEATURES MURELLE GREEN PLANET 110 HE I/E Heat output Nominal (80-60°C) 105,6 Nominal (50-30°C) 114.6 Reduced (80-60°C) 21.1 Reduced (50-30°C) 23.6 Heat input nominal* 108,0 Heat input reduced* 21,6 Max/min useful yield (80-60°C)* 97.7/97.8 Max/min useful yield (50-30°C)* 109.1/106.1 ★★★★...
  • Page 7 FUNCTIONAL DIAGRAM (fig. 2) 13 Pump 1 Gas valve 14 Drain vent 2 Condensate drain trap 17 5 BAR safety valve 3 Heating return sensor (SR) 4 Fan 5 Heating flow sensor (SM) CONNECTIONS 6 Safety thermostat 95°C Heating return 7 Exhaust probe (SF) Heating flow 8 Primary heat exchanger...
  • Page 8 MAIN COMPONENTS (fig. 3) 1 Control panel 2 Fan 3 Ignition electrode Primary heat exchanger 5 Ignition transformer Exhaust probe (SF) 7 Auto Air Vent 8 Heating return sensor (SR) 9 Heating flow sensor (SM) Safety thermostat 95°C 11 Ionisation electrode 12 Pump Fig.
  • Page 9: Installation

    - PAR 9 = See TABLE 1-2-3-3/a. installations, it is important to verify the CO2 “MURELLE GREEN PLANET 110 HE I - E” at MAX and MIN capacity and, if necessary, boilers an be installed in boiler rooms For INSTALLER PARAMETERS see 3.3...
  • Page 10 DIP SWITCH DIP SWITCH GESTIONE IN MODBUS GESTIONE IN CASCATA MODBUS MANAGEMENT 1 2 3 1 2 3 CASCADE MANAGEMENT Fig. 4/a CASCADE mode (fig. 4/b) Electrically connect all boilers in CASCADE mode and set PAR15 accordin- gly (master or slave). (As shown in Fig. 4 / b).
  • Page 11 Fig. 4/b...
  • Page 12 MODBUS mode (fig. 4/c) boiler. - Choose the communication configu- The RS-485 board can be used for In this case, proceed as follows: ration suited to the MODBUS network MODBUS communication every - Set the DIP SWITCH of the RS-485 board (PAR 17 INST) according to Table PAR and the PAR 16 as indicated in the figu- 17 INST.
  • Page 13 MODBUS BOILER VARIABLES LIST Function Variable description Digital variables Boiler CH Enable/Request D R/W Request CH zone 1 Enable DHW preparation Boiler DHW Enable D R/W Not used Boiler Water Filling Function D R/W State CH zone 1 Boiler CH Mode State preparation DHW Boiler DHW Mode Boiler Flame Status...
  • Page 14 CASCADE+MODBUS mode ( g. 4/d) CONNETTORE CABLATO This mode allows for MODBUS commu- (cod. 6319173) nication of at least two boilers in cascade WIRED CONNECTOR (cod 6319173) and is performed by requesting another RS-485 board provided in the kit code 8092244.
  • Page 15 CONNECTING 2.3.2 Filter on the gas pipe where it needs to be protected from water, replace the intake terminal inser- UP SYSTEM The gas valve is supplied ex factory with ted in the flange with terminal code To protect the heat system from dama- an inlet filter, which, however, is not 8089510.
  • Page 16 2.5.4 Maximum usable length in TABLE 2 (see point 3.3 to access gas G20 and 3 m when it is operating on LPG G31. for separate ø 80 ues installer parameters). For vertical ues, it must not be greater The maximum overall length of ø 80 inlet than 5 m straight vertical lines when the 2.5.5 Maximum usable...
  • Page 17 C Type (ø 80 separate pipes) WARNING ! When load loss of the individual accessories connec- 80 mm accessories ted exceeds i 4 mm H2O, to assure correct opera- tion of the appliance, do as follows: Key Code Description Load loss mm H20 - set the installer parameter PAR 9 as indicated in Inlet Exaust...
  • Page 18 90° bend 80/125 8095970 45° bend 80/125 Model Gas H (m) L (m) Murelle Green Planet 110 HE i/e G20 Murelle Green Planet 110 HE i/e G31 NOTE: - The condense recovery (12) should be connected to a waste water drain.
  • Page 19 NOTE The following information is an extract from AS 5601-2004. This information is subject to copyright of the AGA and Standards Australia and is supplied only as a reference. Every installer should have a copy and be familiar with this standard before installing this appliance. MINIMUM CLEARANCES REQUIRED FOR BALANCED FLUE TERMINALS, FAN-ASSISTED FLUE TERMINALS, ROOM-SEALED APPLIANCE TERMINALS OR THE TERMINALS OF OUTDOOR APPLIANCES Openable...
  • Page 20 Respect the L and N polarities and the in the package. It is possible to make earth connection. corrections to the values read by the drill NOTE: SIME declines all responsibility 2.6.3 Remote control CR 73 acting on the PAR 11.
  • Page 21 BOILER ELECTRICAL (fig. 11) SR (5 VDC) SF (5 VDC) SM (5 VDC) EV 1-2 TS (24 VDC) SE (5 VDC) SB/SA (5 VDC) TA1 (24 VRAC) TA2 (24 VRAC) 0...10 VDC OP (24 VAC) RS-485 (24 VAC) Selection TA2 or 0-10 VDC CONNECTOR SPARE PART CODES: F1-2 Fuse (4 AT)
  • Page 22: Characteristics

    PC CONNECTION OFF = Electricity supply to boiler is on but not To be used only with the SIME programming kit and only ready for functioning. However, the protec- by authorised personnel. Do not connect other electronic tion functions are active.
  • Page 23 ACCESS TO INSTALLER’S INFORMATION For access to information for the installer, press the key (3 fig. 14). Each time the key is pressed, the display moves to the next item of information. If expansion boards (MIXED ZONE o INSOL) are connected, the related info will be displayed. If the key is not pressed, the system automatically quits the function.
  • Page 24 29. Display of valve operation with board MIXED ZONE 2 (respectively ON and OFF) 18. Display of heating return temperature sensor (SR) 18. Visualizzazione valore sonda ritorno riscaldamento (SR) 29. Visualizzazione comando chiusura valvola con schedino ZONA MIX 2 (rispettivamente ON e OFF) 19.
  • Page 25 ACCESS TO PARAMETERS INSTALLER INSTALLER’S FAST CONFIGURATION PARAMETERS PAR DESCRIPTION RANGE UNIT OF INC/DEC DEFAULT MEASUREMENT UNIT SETTING For access to the installer’s parameters, Combustion configuration -- = ND “- -” press simultaneously the keys 1 ... 22 or 5 seconds (3 fig. 12). Hydraulic configuration -- = ND “- -”...
  • Page 26 BOILER PAR 2 PARAMETERS INSTALLER Instantanious with diverter valve and flowmeter EXPANSION CARD Instantanious with diverter valve, PAR DESCRIPTION RANGE UNIT OF INC/DEC DEFAULT flowmeter and solar system MEASUREMENT UNIT SETTING Number of expansion boards 0 ... 3 Remote control cylinder with Mix valve stroke time 0 ...
  • Page 27 EXTERNAL SENSOR (fig. 13) If there is an external sensor, the hea- ting settings SET can be taken from the climatic curves according to the external temperature and, in any case, limited to with the range values described in point 3.3 (parameters PAR 22 for zone 1 and PAR 25 for zone 2 and PAR28 for zone 3).
  • Page 28 has not been recognised, the boiler When voltage returns, the boiler will Residual head for the heating system is will lockout (ALL06). automatically start up again. shown as a function of rate of flow in the This may be due to a worn or distor- graph in fig.
  • Page 29 “MURELLE GREEN PLANET 110 HE I - E” WITH COMPENSATOR KIT CODE 8101581 AND TANK “BT” SERIES OPTIONAL (fig. 15) Gas valve Condensation drain trap 3 Heating return sensor (SR) (SM) Heating Flow Sensor 6 Safety thermostat 95°C 7 Exhaust sensor (SF)
  • Page 30: Commissioning, Use And Maintenance

    COMMISSIONING, USE and MAINTENANCE INSTALLATION, SERVICING AND REPAI- 4.5.1(chimney sweep) Any adjustments should be done in RS MUST BE CARRIED OUT BY ONLY AU- With the boiler operating in the ma- small steps and adjustments of no THORISED PERSONS ximum rate condition check that the more than 1/8th of a turn should operational (working) gas pressure be made, waiting at least 1 minute...
  • Page 31 (5 fig. 16): This operation must be performed by MAX power authorised personnel using original (Methane) (Propane) Sime components. The standard display will automatically 9,0 ±0,3 10,2 ±0,3 return after 10 seconds. To convert from natural gas to LPG or...
  • Page 32 ATTENTION Codice/Code 8104940 - 41 Before removing or refitting Modello/Model MURELLE HE 110 R the front panel of the boiler, Matricola/Serial n. 9999999999 open the small upper plastic PAR 1 = 7 (G20) / 15 (G31) door. PAR 2 = 5 Fig.
  • Page 33 4.5.1 Chimney sweep function (fig. 21) To check boiler combustion, press the installer’s key for a few seconds. The chimney sweep function will switch on and will continue for 15 minutes. From that moment, the boiler will start working in heating mode at maximum power, with cut off at 80°C and re-igni- tion at 70°C Warning! Ensure adequate circulation...
  • Page 34 FUNCTIONING ERRORS When there is a functioning error, an alarm appears on the display and the blue luminous bar may become red. Descriptions of the errors with relative alarms and solutions are given below: – LOW WATER PRESSURE ERROR ALARM 02 (fig. 23/a) If the pressure detected by the tran- Fig.
  • Page 35 – SAFETY/LIMIT THERMOSTAT ERROR ALARM 07 (fig. 23/f) If either the 95 degree stat or the heat exchanger safety stat opens, the bur- ner will turn off and ALL 07 will be displayed. If the thermostat connec- tion is restored within the minute, the boiler will start up working normally again, otherwise it will stop and the display will show the alarm “ALL 07”.
  • Page 36 – FAN ERROR “ALL 22” (fig. 23/s) circuited, on the display the anomaly “ALL 15” (fig. 23/n) When a mixed zone board is connec- ALL 26 appears. During this anomaly If the fan speed is not within the ra- ted to the boiler, an intervention of the the boiler continues to function nor- ted speed range, the display will show safety thermostat switches the mixed...
  • Page 37 – HEATING RETURN SENSOR ERROR – RS-485 COMUNICATION ERROR IN CASCADE MODE “ALL 30” (fig. 23/v) When the heating return temperature “ALL 34” (fig. 23/x) sensor(SR) ids open or short circuited When il PAR 15 is different from “- -” and the display shows ALL30.
  • Page 38: User

    USER INSTRUCTIONS WARNINGS – In case of fault and/or incorrect equipment operation, deactivate it, without making any repairs or taking any direct action. Apply only to qualified technical personnel. – Boiler installation and any other assistance and/or maintenance activity must be carried out by qualified per- sonnel registered as a gas technician.
  • Page 39 Standard display will return by pressing again, or after 10 seconds if the key Circuito no key is pressed. riscaldamento 2 Heating circuit 2 Regulation of the external sensor (fig. 25/a) If an external sensor is installed, the value of the output temperature is au- tomatically chosen by the system, which Circuito quickly adjusts the environmental tem-...
  • Page 40 (2) to re-start the boiler. – ALL 14 MAINTENANCE If the anomaly persists, request Request assistance from quali- Annual maintenance of the appliance assistance from qualified techni- fied technical personnel. should be planned sufficiently in advan- cal personnel. ce, and can only be done by registered, –...
  • Page 41: Boiler Registration

    LOG BOOK - Installation, Commissioning and Service 1. Installation Details Owner -name Installation Address -Street City State Installation Phone Number Contact and Phone Number Sime Product - Model Serial Number refer to data plate ❏ ❏ ❏ ❏ Gas Type Natural Gas...
  • Page 42 COMMISSIONING BOILER CHECK LIST A suggested method of commissioning the boiler, actual method can vary according to the boiler make type and the installation. The boiler must always be installed , and commissioned by an qualifi ed gas technician. The installer certifi es that this Boiler has been installed to the manufacturer’s instructions, has been fi lled, commissioned and is ready for use.
  • Page 43 Handover Instructions ✔ No. Description when done Fill in all the details on this Boiler manual Instruct the owner/users on the correct operation of this heating system, this includes how to turn the system on and off, adjust the time and temperature settings. How to turn the heating system off in summer and on for winter.
  • Page 44: Service Record

    SERVICE RECORDS Service – 1 – year 1 Date Service technician Name PIC Licence No. Service Company Contact phone number Work Completed Note Service – 2 – year 3 Date Service technician Name PIC Licence No. Service Company Contact phone number Work Completed Note Service –...
  • Page 45 Service – 5 – year 9 Date Service technician Name PIC Licence No. Service Company Contact phone number Work Completed Note Service – 6 – year 11 Date Service technician Name PIC Licence No. Service Company Contact phone number Work Completed Note Service –...
  • Page 48 HUNT HEATING HYDRONIC SYSTEMS ( AUSTRALIA) PTY LTD 11 Fiveways Boulevard, Keysborough, Victoria 3173 Telephone 1300 00 1800 Facsimile 9798 5133 www.huntheat.com.au...