Commissioning

4
Commissioning
4.1

Commissioning checklist

1
Outdoor unit and indoor unit are correctly installed.
2
Pipes are correctly
• connected,
• thermally insulated,
• and checked for tightness.
3
Condensate pipes are functioning correctly and
have been tested.
4
Electrical connection has been correctly
established.
• Power supply is in the normal range
• Protective conductor is properly attached
• Connection cable is securely attached to the
terminal strip
5
All covers are fitted and secured.
6
The horizontal louver of the indoor unit is fitted
correctly and the actuator is engaged.
Table 8
4.2

Functional test of device

The system can be tested once the installation including tightness test
has been carried out and the electrical connection has been established:
▶ Connect the power supply.
▶ Switch on indoor unit with the remote control.
▶ Hold the ON/OFF [1] key pressed for 5 seconds to set the
Cooling mode ( Fig. 21)
A beep sounds and the ON indicator flashes.
▶ Test cooling mode for 5 minutes.
▶ Ensure freedom of movement of air baffle [2].
▶ Select the heating mode on the remote control.
▶ Test heating mode for 5 minutes.
▶ Press the ON/OFF key again to stop the operation.
4.3

Handover to the user

▶ When the system has been set up, hand over the installation manual
to the customer.
▶ Explain to the customer how to use the system, referring to the
operation manual.
▶ Advise the customer to carefully read the operation manual.
38
Climate Class 6000i/8000i – 6721831489 (2021/02)

Advertisement

Table of Contents
loading

This manual is also suitable for:

Climate class 8000iClc6001i-set 25 heClc6001i-set 35 heClc8001i-set 25 he tClc8001i-set 25 he sClc8001i-set 25 he r ... Show all

Table of Contents