The installation of the LIN-300 metal protection box involves three main steps:
1. Preparing the holes for the connectors and grounding assembly;
2. Fastening the protection box;
3. Grounding the protection box.

3.2.5 Preparing the holes for the liquidtight connectors and grounding assembly

Figure 13 : Removing the mounting panel and anti-vibration mounts
24
LIN-300 Protection Boxes_Installation - Rev. 0
1. As
a
precaution
protection box, remove the mounting panel
to prevent metal particles infiltration. Do not
misplace the anti-vibration rubber mounts
added to the mounting panel assembly.
Copyright © VibroSystM Inc., 2010
before
drilling
the

Advertisement

Table of Contents
loading

This manual is also suitable for:

Lin-300 seriesLin-304s-6i-0.3/4.3Lin-306s-6i-0.3/6.3

Table of Contents