The installation of the LIN-300 ABS protection box involves two main steps:
1. Preparing the holes for the connectors;
2. Fastening the protection box.
3.1.5 Preparing the holes for the liquidtight connectors
SIDE A
1.19'' [30mm]
Figure 4 : Suggested location for liquidtight connector holes
Figure 5 : Mounting the liquidtight connectors on ABS protection box
Copyright © VibroSystM Inc., 2010
SIDE A
1.19'' [30mm]
CL
Hole:1 1/8''[28.5mm]
1. To prevent damage, remove the LIN conditioner
before drilling the protection box. Do not misplace
the anti-vibration rubber mounts added to the
mounting brackets.
Before deciding on the location for the holes, make
sure that the liquidtight connectors will not be too
close to the LIN conditioner once it is reinstalled,
and that the cables will not be kinked.
2. Drill holes and install the the liquidtight connectors.
Refer to Figure 5 : "Mounting the liquidtight
connectors on ABS protection box".
LIN-300 Protection Boxes_Installation - Rev. 0