Pull the rudder cables forward and under the pulleys at Station 3. Install Small
Cotter Pins to retain the cables. Continue to route cables forward under the
pulleys between Station 2 and 2A. Bolt the small pulleys in place and check for
free movement.
10.
Install the forward cable/pulley as shown on the PARTS MANUAL DRAWING.
11.
Bolt the Multi-Hole Tang on the forward cable to lower hole in Horn on Rudder
Pedals.
NOTE: The Multi-Hole Tang has several holes which may be used to
adjust for equal tension of the Rudder Cables.
12.
Attach Rudder Cables to top hole of Rudder Cable Horns on Rudder Pedals.
13.
Check that the cables run through all pulleys and guides. Check for free
movement and centering of the Rudder.
14.
For final adjustment and checks of the rudder system, refer to RIGGING.
(AFTER SKINNING AND PAINTING OF FUSELAGE AND INSTALLATION OF
FIREWALL)
1.
Rudder pedals and floorboards must be installed and the airplane should be
on the main gear with wheel assemblies mounted.
2.
Drill the arm of Parking Brake to 1/4".
3.
Locate the holes in the firewall for the Parking Brake, Brake Reservoir and
Bulkhead Tee per FIGURE 09C-03. Install these after the soundproofing has
been installed on the firewall.
4.
Install fittings in the brake cylinders as per parts manual using thread
sealant. Refer to FIGURE 09C-04.
5.
Bolt brake cylinder to the fuselage tangs and to the Rudder Pedal Cylinder
Attach Brackets as shown in the parts manual. Do NOT forget the cotter
pins securing the bolts.
6.
Check that the pedals and the brake pedals move freely.
7.
Route brake lines and install to cylinders, park brake valve and "T" fitting as
per FIGURE 09C-04.
8.
Locate brake line exit holes in Fuselage Bottom Skin per FIGURE 09C-08.
Install 90-degree Bulkhead Elbow. Route brake lines from Park Brake Valve
to 90-degree Bulkhead Elbow.
9.
Connect lines to the fittings on the wheel assembly. Press into groove on aft
side of landing gear and connect to Bulkhead Elbow.