Daikin Altherma 3 R F Installer's Reference Manual page 223

Hide thumbs Also See for Altherma 3 R F:
Table of Contents

Advertisement

Energy metering
ERLA11~16DAV3+W1 + EBVH/X11+16S18+23DJ
Daikin Altherma 3 R F
4P643602-1 – 2021.09
NOTICE
2 weeks to change. After you activated BBR16, you only have 2 weeks to change its
settings (BBR16 activation and BBR16 power limit). After 2 weeks, the unit
freezes these settings.
Note: This is different from the permanent power limitation, which is always
changeable.
BBR16 activation
#
[9.9.F]
[7-07]
BBR16 power limit
#
[9.9.G]
[N/A]
Energy metering
If energy metering is performed by the use of external power meters, configure the
settings as described below. Select the pulse frequency output of each power
meter in accordance with the power meter specifications. It is possible to connect
up to 2 power meters with different pulse frequencies. If only 1 or no power meter
is used, select 'None' to indicate the corresponding pulse input is NOT used.
#
Code
[9.A.1]
[D‑08]
[9.A.2]
[D‑09]
Code
BBR16 activation:
0: disabled
1: enabled
Code
BBR16 power limit: This setting can only
be modified via the menu structure.
0 kW~25 kW, step 0.1 kW
Electricity meter 1:
0 None: NOT installed
1 1/10kWh: Installed
2 1/kWh: Installed
3 10/kWh: Installed
4 100/kWh: Installed
5 1000/kWh: Installed
Electricity meter 2:
0 None: NOT installed
1 1/10kWh: Installed
2 1/kWh: Installed
3 10/kWh: Installed
4 100/kWh: Installed
5 1000/kWh: Installed
In case of pulse meter for photovoltaic panels:
6 100/kWh for PV panel: Installed
7 1000/kWh for PV panel: Installed
11
Configuration
|
Description
Description
Description
Installer reference guide
223

Advertisement

Table of Contents
loading

Table of Contents