Ceraphant T PTC31, PTP31, PTP35
6
Commissioning
6.1
Function check
Carry out a post-installation and a post-connection check as per the checklist before
commissioning the device.
• "Post-installation check" checklist see Section 3.3
• "Post-connection check" checklist see Section 4.4
6.2
Basic settings
Base
Basic settings
Endress+Hauser
Technical unit
Configure zero point
Accept zero point
Display
Damping:
display value, output signal
DESINA
Commissioning
Select technical unit:
bar
psi
kPa/MPa
%
Offset:
±20 % URL
Current value as zero point (Offset
max. ±20 % URL)
PV: measured value display
PVRO: measured value display
rotated 180°
SP: set switch point display
SPRO: set switch point display
rotated 180°
OFF: display off
OFFR: display off rotated 180°
0...40 s
in increments of 0.1 s
Connection in accordance with
DESINA guidelines
(see Section 4)
15