10.2 Maintenance schedule

Maintenance

Changing the Service-Unit

Cleaning
Functional test
Visual inspection
Leakage test
* based on 7 bar(g) (101.5 psi(g)) and pH-neutral condensate

10.3 Maintenance work

For assembly work to be carried out, the following prerequisites must be fulfilled and the preparatory tasks must have 
been completed.
Tools
Screwdriver – flat head
size 2.5 mm (0.09")
Spanner or adjustable end wrench
10.3.1 Changing the Service-Unit
Illustration
X1
X2
Interval
After 2 x 8760 operating hours or 1 million switching cycles*; at least every 2 years
Annually
Monthly
Weekly
After assembly and maintenance works on the product
Prerequisites
Material
Sealants
Lubricant for greasing the O-rings
Mild detergent
Cotton or disposable cloth
BEKO TECHNOLOGIES
Service-Unit
BEKO TECHNOLOGIES set of seals
Exchange work
Always to be worn:
Description / explanation
1. Interrupt the condensate feed via the condensate inlet
line [X1] (e.g. by closing the recommended shut-off 
valve [X2]).
BEKOMAT
33iU / 33iU CO
®
Protective equipment
45 | 68