To Begin Processing Material MAINTENANCE General Clean Up Inspection and Preventative Maintenance Checklist 19-21 Replacing Brushes Air Assembly De-Duster Chamber Access Hatch PARTS AND SERVICE 25-26 Service Contact Information Serial Number Location Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
For safety reasons, and for your own best use of the Baker M6 Sidewinder DeDuster, we insist that you read this manual fully, and constantly review and refer back to it as necessary.
Schematic A structural or procedural diagram, typically of an electrical or hydraulic system To generate a return for effort, an amount produced Yield Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
CEO or Sales Manager of Baker Products. Our one (1) year warranty period covers all items built at our manufacturing facilities including structural frame, cowlings, doors, shafting, dust chutes and guards.
No list of safety expectations can ever be complete as every work environment is as different as are the people operating the equipment. Always keep safety as your highest priority and always use this machine with caution and respect. Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
1. Failure to stop equipment 2. Failure to disconnect from a power source 3. Failure to dissipate (bleed, neutralize) residual energy 4. Accidental re-starting of equipment 5. Failure to clear work areas before re- starting Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
MACHINE FEATURES We want to highlight the unique and special features of the Baker M6 Sidewinder DeDuster. Heavy-duty steel construction Powerful electric motors Air driven material pusher Easy to set-up and fast feed speed Heavy-duty nylon...
Efficient dust and chip removal requires a minimum of 1,500 CFM suction at the machine dust removal chute. This is an end user/owner responsibility. Note: Failure to provide proper vacuum or suction may result in damage to machine or operations personnel. Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
All five (5) of these listed items together make Guards up the safety system. Failure of any one of these factors will increase accident potential. Devices Instructions ’ ’ Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Align the mark to the appropriate material length, and then re- tighten the (3) nuts and bolts (Figure 15A). Note: There are notches between each set of material length numbers for 2-inch adjustment increments. Figure 15A Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
When proper bottom brush height is achieved, re-tighten the jam nuts on each side. Jam nuts Jam nuts Jam nuts Jam Nut Bottom brush height Bottom brush height adjustment nut adjustment nut Figure 16B Figure 16C Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Page 17
Reference Figure 16A. When proper top brush height is achieved, re-tighten the jam nuts. Figure 17 Jam nuts Jam nut Top brush height adjustment bolt Figure 17A Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Note: Incoming material should not be stacked higher than the height of the fence / guide. ALL STOP BRUSH START FEED START FEED STOP Figure 18 Incoming material should not be stacked higher than the height of the fence / guide Figure 18A Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Grease the material pusher linear rail bearings. We recommend JT-6 grease (no Weekly more than 3 pumps). Grease bearings using high temperature grease. We recommend JT-6 grease (no Every 3 Months (Approx 480 hrs) more than 5 pumps). Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Page 20
Increase or decrease chain Increase or decrease chain tension here tension here tension here (1) chain per side, (2) total (1) chain per side, (2) total (1) chain per side, (2) total Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Page 21
(2) per side (4) total (2) per side (4) total Figure 21 EVERY 3 MONTHS - Grease bearings using high temperature grease. We recommend JT-6 grease (no more than 5 pumps). Figure 21B Figure 21C Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Complete a visual inspection to ensure all other guards/covers are in place and secure prior to resuming operation. Hatch cover nuts Hatch cover nuts Hatch cover nuts Hatch cover nuts (4) total (4) total (4) total (4) total Hatch cover Figure 24 Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Bimba air cylinder; 1- 1/4” street tee (brass 1/2” x 10” pipe fitting) 241112 241156 1/4” x 1/8” hose barb Norgren 1/4” filter/reg w/bracket 241198 241312 Air tank – 5 gallon Norgren 4-way solenoid valve Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
Page 26
Electric N/C c-block red Electric N/C c-block green 101224 101276 Linear block SR30 Linear rail 161233 667795 Deduster brush; tube Strip brush 5/16” x 3” H style 12” OD x 62” wide x 6’ L Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...
The model and serial number are located on the front side of the machine near the material entry conveyor. Please refer to your serial number and model number when speaking to a service technician or ordering replacement parts. Baker M6 DeDuster - Rev 1, 11/07; WWW.BAKER-ONLINE.COM...