Figure B-17 Installation flowchart of the B68-22 cabinet (on raised floor)
B.3.3 Support Positioning
I. Planning the cabinet position
Before the installation, first plan the available space. There should be sufficient space
for maintenance and operation at the front and rear doors of the cabinet, as shown in
Figure B-19, Figure B-20 and Figure B-21. At least 800mm clearance is required
around the B68-22 cabinet.
II. Drawing lines
According to the reference dimension and support dimension in the construction plane
design diagram, determine the support installation location, measure several
marking-out points, mark out two lines which are parallel with the reference and whose
spacing is 760mm. According to the design requirements, determine the hole locations
of the first support on the two lines. Then take the hole as the reference point and mark
out the installation holes of other supports one by one. To avoid faults, after being
marked out, all hole location lines should be measured again so as to ensure the proper
dimension. Figure B-18 shows the support installation hole locations, Figure B-19
shows the installation hole locations of a single cabinet, Figure B-20 shows the
Start
Start
Support positioning
Support positioning
Install support
Install support
Install slide rail
Install slide rail
Level cabinet
Level cabinet
Fasten cabinet
Fasten cabinet
Insulation test
Insulation test
Test passed?
Test passed?
Y
Y
Recover floor
Recover floor
End
End
Appendix B Installation of B68 Cabinet
N
N
B-17