CAME FROG-PM4 Installation Manual

CAME FROG-PM4 Installation Manual

Underground operator for swing gates
Hide thumbs Also See for FROG-PM4:

Advertisement

Quick Links

UNDERGROUND OPERATOR
FOR SWING GATES
FA 00597 -E N
INSTALLATION MANUAL
FROG-PM4 / FROG-PM6
EN
English

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the FROG-PM4 and is the answer not in the manual?

Questions and answers

Summary of Contents for CAME FROG-PM4

  • Page 1 UNDERGROUND OPERATOR FOR SWING GATES FA 00597 -E N INSTALLATION MANUAL FROG-PM4 / FROG-PM6 English...
  • Page 2 WARNING! important safety instructions: READ CAREFULLY! • REMISE PREVENT POTENTIALLY HAZARDOUS SITUATIONS EAD THE INSTRUCTIONS IF THE POWER • E MPLOY THIS PRODUCT ONLY FOR THE USE FOR WHICH IT WAS EXPRESSLY MADE SUPPLY CABLE IS DAMAGED IT MUST BE REPLACED BY THE MANUFACTURER OR AUTHORIZED .A.
  • Page 3: Intended Use

    ARE IN MILLIMETERS DESCRIPTION FROG-PM4 Irreversible gearmotor - with encoder - for swing gates with 5.5 m long leaves, with adjustable closing-leaf stop. FROG-PM6 Irreversible gearmotor - with encoder - for swing gates with 7.0 m long leaves, with adjustable closing-leaf stop.
  • Page 4 Dimensions Description of the components 1. Gearmotor 2. Transmission lever 3. Gearmotor arm 4. Adjusting screw for closing limit switch UNI 5739 M12x120 5. Couple release lever 6. Gate mounting bracket 7. Adjusting screw for opening limit switch UNI 5739 M12x70 8.
  • Page 5: General Installation Instructions

    Example of a system 1. Gearmotor with foundation box 2. Control panel 3. Junction box 4. Key selector 5. Antenna 6. Flashing light 7. Photocells 8. Photocell posts 9. Latch 10. Inspection chamber 11. Drainage chamber 12. Mechanical stop GENERAL INSTALLATION INSTRUCTIONS ⚠...
  • Page 6: Installation

    Tools and materials Make sure you have all the tools and materials you will need for the installation at hand to work in total safety and compliance with current standards and regulations. The figure shows some examples of installer’s tools. Types of cables and minimum thicknesses Cable Cable length...
  • Page 7 Laying the corrugated pipes and inspection chambers Make the hole for the box. Prepare the junction boxes and corrugated pipes necessary for connection to the inspection chamber and the drain pipe.  the number of tubes depends on the type of system installed and any accessories. Installing the foundation box Lean the box against the pillar making sure that the corrugated pipes and the drain pipe pass through the designated holes.
  • Page 8 Lubricate the foundation case pin, the latch and the gate bracket pin. Install the gate leaf, inserting the upper hinge. Fix or carefully weld the leaf to the fixing bracket to the gate. Check that the leaf opens and closes without difficulty. Securing the release It is important to lubricate the release latch, for fixing and operation, check the information entered in the manual of the device selected.
  • Page 9: Fastening The Gearmotor

    Fastening the gearmotor   Before fastening the gearmotors, fit the adjusting screws into the gearmotor drive arms, as shown in the drawing. RIGHT SIDE LEFT SIDE Open the door to facilitate the placement of the gearmotor in the foundation case and its anchoring. Secure the gearmotor using the nuts supplied.
  • Page 10 Lubricate the transmission lever and fit it into the hole of the gearmotor arm and case lever. Determining the end run points During opening: - Fully open the leafs (the maximum aperture is 110 °);   - loosen the screw until it makes contact with the body ...
  • Page 11: Electrical Connections

    Electrical connections ⚠ For electrical connection operations follow the information in the control panel technical documents. M1 - 230 V AC delayed-opening gearmotor. M2- 230 V AC delayed-closing gearmotor. IP67 junction boxes (not supplied) Blue Blue Brown (*) Brown (*) Black (*) Black (*) Yellow / Green...
  • Page 12: Final Operations

    FINAL OPERATIONS Securing the cover Rest the cover on the foundation box and secure using the screws (supplied) M8x20 screws UNI 5933 LEAF MANUAL RELEASE ⚠ Manually releasing the gate may cause an uncontrolled movement of the gate due to possible mechanical anomalies or unbalancing. RELEASING Insert the key/lever into the release lock and turn it counter-clockwise.
  • Page 13: Troubleshooting

    INSTALLING AND CONNECTIONS FOR OUTWARD-OPENINGS Below are the only procedures that vary compared to standard installations: Fastening the gearmotor Before fastening the gearmotors, fit the adjusting screws into the gearmotor drive arms, as shown in the drawing. LEFT RIGHT TROUBLESHOOTING MALFUNCTIONS POSSIBLE CAUSES CHECKS AND REMEDIES...
  • Page 14: Periodic Maintenance

    MAINTENANCE ☞  Before any maintenance, disconnect power to prevent any possible dangerous situations that can be caused by accidental movement of the operator. Lubricate the pivot points with grease whenever abnormal vibrations or squeaking occurs, as shown in the figure. Periodic maintenance Periodic maintenance log to be completed by the user (every six months) Date...
  • Page 15: Dismantling And Disposal

    ☞  CAME S.p.A. implements an EN ISO 14001-certified and compliant Environmental Management System at its plants, to ensure environmental protection. Please continue our efforts to protect the environment, something that CAME considers to be one of the foundations in developing its business and market...
  • Page 16 CAME S.p.A. CAME S.p.A. Via Martiri Della Libertà, 15 Via Cornia, 1/b - 1/c 31030 Dosson di Casier Dosson di Casier 33079 Sesto al Reghena Sesto al Reghena Treviso Treviso - Italy Pordenone Pordenone - Italy (+39) 0422 4940 (+39) 0434 698111...