11 Field Settings

11.1 Initial Unit Preparation and Installation Checklist

WARNING:
 This checklist is NOT to be used in place of the Installation,
Operation, and Maintenance Manual.. Please refer to
Installation, Operation, and Maintenance Manual for
specifications and detailed installation requirements.
No.
Setting Up the Unit
1
Be sure to consider maximum lineset lengths
Ensure proper clearances and location restrictions for
2
outdoor and indoor unit
3
Ensure outdoor unit is installed on a pad
No.
Check Refrigerant Lines
1
Ensure proper lineset diameters
2
Ensure proper insulation and routing
3
Braze refrigerant lines using proper techniques
4
Perform leak check
5
Properly evacuate lines
6
Open service valves, ensure they are fully open
No.
Low Voltage Wiring
1
Ensure low voltage wiring does not exceed maximum length
2
Ensure proper gage wire is used
Connect thermostat wiring as shown in wiring diagrams in
3
IOM
No.
High Voltage Wiring
Connect high voltage power supply ensuring proper safety
1
precautions are followed
2
Install high voltage disconnect switch
3
Ensure proper grounding on indoor and outdoor units
Table 22
Bosch Thermotechnology Corp. | 07.2021

11.2 Initial Start-up Checklist

WARNING:
 This checklist is NOT to be used in place of the Installation,
Operation, and Maintenance Manual. Please refer to
Installation, Operation, and Maintenance Manual for
specifications and detailed installation requirements.
No.
System Start-up
Consider non-default dipswitch positions as needed, refer to
1
section 11.3.2 and 11.3.4
2
Set thermostat to OFF prior to unit charging
No.
Unit Charging
Determine proper charging method: weigh in method or
1
charge by subcooling. If design superheat and subcooling
cannot be achieved, refer to section 13.9 for troubleshooting.
After 20 minutes of unit operation, ensure proper drainage of
2
condensate on indoor and outdoor units
3
Force unit into Manual Defrost to verify functionality.
Table 23

11.3 Dip Switch Settings

11.3.1 Outdoor Unit Dip Switch Settings

SW4
SW5
J2
Figure 10
3 Ton
Bosch IDS 2.0 | 33
USB
SW1
SW3
SW2
Data subject to change