SBTL9000 Series
Version: 1.0
Due to regular upgrades of systems and products, ZKTeco could not guarantee exact consistency between the
actual product and the written information in this manual.

Advertisement

loading

Summary of Contents for ZKTeco SBTL9000 Series

  • Page 1 Installation Guide SBTL9000 Series Version: 1.0 Due to regular upgrades of systems and products, ZKTeco could not guarantee exact consistency between the actual product and the written information in this manual.
  • Page 2: Installation Requirements

    The installation position of the swing barrier turnstile depends on its size. A distance of 100mm between the swing barrier turnstile and the wall needs to be reserved for ease of opening the top cover of the machine to perform maintenance and adjustment. The reference €gure is shown below: Figure 2-1 SBTL9000 Series Dual-lane...
  • Page 3 3 Preparation Tools: A measuring tape, an adjustable wrench, an impact drill and a small screwdriver (included in the package). Material: A PVC anti-€re and insulation tube (diameter∫ 25mm), standard three-core power extension wire, tether cable (random con€guration), M12 expansion screws (included in the package).
  • Page 4: Installation

    4 Installation Prepare the tools for product installation and sort out the auxiliaries according to the packing list. Mark the screw hole at the centre of the stand, and the edge of the chassis base on the ground according to the sizes as shown on the Figure 4-1. Drill the holes with Ј...
  • Page 5 PVC conduits are laid 100mm under the ground, with the height of the exposed part not exceeding 100mm. In addition, the conduit outlet is bent back to prevent the ingress of water into the conduit. SBTL9000 series installation holes and cabling positions is shown in Figure 4-3: Air Switch...
  • Page 6 Connect the online cables and perform the power-on test. Wait for 10 seconds for the turnstile to complete the self-test program. At the same time, check if the indicators work properly. If everything works €ne, you can tighten the screws and €x the device. If an exception occurs, please contact your vendor.
  • Page 7: Wiring Diagram

    5 Wiring Diagram Below is the wiring diagram: RS485 RS485...
  • Page 8 ZKTeco Industrial Park, No. 32, Industrial Road, Tangxia Town, Dongguan, China. Phone : +86 769 - 82109991 : +86 755 - 89602394 www.zkteco.com...