Luffing Jib Raising Procedure
Luffing Jib No. 149A On Boom No. 57
15000 SERIES 3 equipped with 99 740 kg crane counterweight and 36 290 kg carbody counterweight and 15000 SERIES 4
equipped with 107 680 kg crane counterweight and 52 160 kg carbody counterweight for raising and lowering boom and luffing jib
combinations. Refer to luffing jib rigging assembly No. A08947 for proper make-up of inserts, straps, pendants and miscellaneous
parts, etc. and to luffing jib operator's manual.
Two methods may be used to raise and lower boom and luffing jib combinations.
A. Layout In-Line Method
Boom and luffing jib are assembled in layout, end to end, position. Boom and luffing jib must be inline over end of blocked
crawlers prior to raising boom and luffing jib. Slowly raise boom until angle between boom to luffing jib is approximately
172 degrees. Jib stop pins should engage automatically when inner strut is fully retracted. Visually observe that these pins are
fully engaged before raising boom and jib. Tighten luffing jib suspension with luffing jib hoist. Boom and luffing jib can then
be raised simultaneously using only the boom hoist. Reverse this procedure when lowering boom and luffing jib.
Boom and luffing jib combinations in table below may be raised and lowered using layout in-line method.
Recommended boom and luffing jib raising and lowering procedure
LAYOUT IN-LINE METHOD - 15000 SERIES 3, 4
Maximum Boom and Luffing Jib Lengths Lifted Unassisted
Over End Of Blocked Crawlers
Boom Length
Intermediate Fall
Feet
Meters
Feet
80.4
24.5
70 - 190
90.2
27.5
70 - 180
100.1
30.5
70 - 170
109.9
33.5
70 - 160
119.8
36.5
70 - 150
129.6
39.5
70 - 130
139.4
42.5
70 - 120
149.3
45.5
70 - 100
159.1
48.5
70 - 80
169.0
51.5
70
Load blocks, hook and weight ball on ground until boom and luffing
jib are erected.
15000 SERIES 3, 4
Luffing Jib No. 149A
Without
Intermediate Fall
Meters
Feet
21.3 - 57.9
70 - 180
21.3 - 54.9
70 - 170
21.3 - 51.8
70 - 160
21.3 - 48.8
70 - 150
21.3 - 45.7
70 - 130
21.3 - 39.6
70 - 120
21.3 - 36.6
70 - 110
21.3 - 30.5
70 - 90
21.3 - 24.4
70
21.3
With
Meters
21.3 - 54.9
21.3 - 51.8
21.3 - 48.8
21.3 - 45.7
21.3 - 39.6
21.3 - 36.6
21.3 - 33.5
21.3 - 27.4
21.3
8631-A, 8-12-05/GA
Page 1 of 3

Advertisement

loading

Summary of Contents for Manitowoc 15000 3 Series

  • Page 1 Manitowoc Cranes, Inc. Manitowoc, Wisconsin 54220 U.S.A. Luffing Jib Raising Procedure 15000 SERIES 3, 4 Luffing Jib No. 149A On Boom No. 57 Recommended boom and luffing jib raising and lowering procedure 15000 SERIES 3 equipped with 99 740 kg crane counterweight and 36 290 kg carbody counterweight and 15000 SERIES 4 equipped with 107 680 kg crane counterweight and 52 160 kg carbody counterweight for raising and lowering boom and luffing jib combinations.
  • Page 2 Manitowoc Cranes, Inc. Manitowoc, Wisconsin 54220 U.S.A. Luffing Jib Raising Procedure 15000 SERIES 3, 4 Luffing Jib No. 149A On Boom No. 57 B. Layout Jack-Knife Method Longer boom and luffing jib combinations must be raised and lowered using this method.