46/68
Bosch Rexroth AG
Set-up, installation and commissioning
Connection
9.2
Check the pneumatic supply
The mMS 4.0 training system is completely pre-assembled and tested at the
factory. During transportation, however, faults or damage may arise on the mMS
4.0 training system.
Before commissioning of the pneumatic system always check
the hose system for damage;
the proper seating of the hose couplings;
whether any of the parts can be damaged;
whether all of the attachment parts are properly connected;
Fig. 19: Pneumatic diagram profile trolley
Connect each station's maintenance unit to the air supply which is on
the extreme left.
Next, connect the stations together by making a connection between
the shutoff valve on each station with the maintenance unit of the next station.
Fig. 20: mMS 4.0 installation
Observe the shutoff valves for the air supply on each station.
The air supply is passed on from each station to the next.
The pneumatic circuit diagrams of each station can be found in the enclosed
documentation CD.
Training system mMS 4.0 | R901429162/04.16