2. Mounting of the primary protection tube / 3. Integrity check
9. Once the thermocouple is mounted centrally on the flange nozzle, it can be carefully
aligned for the electrical connections and, if necessary, purge gas connections by
turning it. Now fit and tighten the flange bolts using skilled personnel.
10. Now the electrical connections and, if necessary, the purge gas connections can be
made.
3. Integrity check
We recommend carrying out the integrity check of the installed thermocouple after
installation and before commissioning the reactor. This will ensure that no damage has
occurred to the measuring instrument and that the purge gas connection has been made
correctly.
This test should be carried out as soon as possible after the installation of the
thermocouple so that, in the event of a damaged measuring instrument, a replacement
measuring instrument can be supplied before the reactor is commissioned, as it is
generally not possible to replace the measuring instrument during operation.
WIKA additional operating instructions for installation of models TC82, TC83 Calitum
EN
9
®