Table 1 Initial Configuration Parameters for Power Supply and Distribution Devices
Device Name
Project Configuration
Integrated UPS
■Involved □Not involved
MCCB
■Involved □Not involved
Electric heating
■Involved □Not involved
Note: The following device parameters are not all parameters of the devices. Only the parameters that need to be set for the project are listed. Default values will be used for the other parameters so they do
not need to be set. To view other device parameters, see the user manual for the corresponding device.
If voltage/frequency settings for power distribution devices are involved, adjust the voltage and frequency settings based on the local voltage system and check whether the voltage thresholds and frequency
hysteresis meet setting requirements before first operation.