Installation Sequence
Installing Pre-fab. Modules (Base Solution)
Installing a Pre-fab. Module
Grounding Pre-fab. Modules
Installing the Drainage Sheet Metal
Component for the Intelligent Heat
Installing External
Exchanger
Accessories for the Pre-fab.
Module
Installing Awnings
Installing Air Conditioner
Installing Air Conditioner Drainpipes
Drainpipes
Installing Power Supply and Distribution
Devices
Installing Devices Inside the
Pre-fab. Module
Installing Monitoring Devices
Installing Fire Extinguishing Devices
Connecting External Cables
Installing External Input Power Cables
Checklist of Devices Installed Onsite
Subcategory
Installing Pre-fab. Module Bases
Removing the Pre-fab. Module Cover
Hoisting and Securing Pre-fab. Modules
Grounding Pre-fab. Modules
Installing the Drainage Sheet Metal Component for the
Intelligent Heat Exchanger
Installing Awnings
Installing a dehumidifier drainpipe
Installing Power Modules
Installing Lithium Batteries
Installing a ground cable
Installing a Light
Installing the socket
Installing Monitoring Devices
Installing CE-Certified Fire Extinguishing Devices
Installing External Input Power Cables
Item
Diagram ID
No.M004
Diagram Name
Site Space And Pre-fab. Module Installation
NO.S002
Position Diagram (Single-capacity Base
Scenario)
Pre-fab. Module Grounding Position
NO.S003
Diagram
(Optional) Installation Position Of The
NO.S007
Drainage Sheet Metal Component For The
Intelligent Heat Exchanger
(Optional) Awning Installation Position
NO.S008
Diagram
NO.S004
(Optional) Humidifier Pipe Layout Diagram
No.P017
Power module installation position diagram
Lithium battery installation position
No.P018
diagram
No.P011
Grounding System Wiring Diagram
No.P012
Light Power Cable Wiring Diagram
Socket And Light Switch Power Cable
No.P013
Wiring Diagram
Monitoring Device Installation Position
Diagram
(Optional) RF_Z Antenna Installation
No.S021
Position Diagram
Fire Extinguishing Device Installation
No.F004
Position Diagram (CE)
Wiring Diagram From The Mains to The
No.P009
Power PDF