A checklist must be completed during the drive wiring process. See Appendix for terminal locations. Power Perform the following to connect power. See the C4 Controller sheet 03 Machine Room for job specific information. • Connect main line power to terminal blocks L1/L2/L3.
All safety inputs are functional during Construction mode on the C4 product. When these safety devices are installed, they are connected per the C4 Controller sheet 02 Machine Room I/O of the prints, even if still on Construction mode. The following includes instructions for when none of these devices have been installed prior to beginning on Construction mode.
Perform the following to power up the drive. Apply external power by closing the main disconnect. Close the two-pole breaker and all pushbutton breakers. Verify the LCD on the Smartrise board and the Magnetek Drive powers up. Figure 5: Breakers Closed Loop Induction Motor Quick Start-Up Guide This quick start-up guide outlines the general parameters that must be changed/verified when a drive is installed with information that is readily available.
Make sure the car is moving without triggering a fault either on the Smartrise MR board or the drive. If the MR board is faulted, see the C4 User Manual. If the drive is faulted, see the Magnetek M1000 Manual.
A and A/ encoder wires. Brake Not Lifting If the brake is not picking, make sure that the brake is wired according to C4 Controller sheet 05 Brake Connection and if there is a second brake installed, verify that the EB terminal is jumpered to the terminal.