USC Surge Hopper Operator's Manual page 18

Table of Contents

Advertisement

7. Attach 4 leg assemblies to the scale
frame using 5/8-11 X 2.0" grade 5
bolts with a washer under the head of
the bolt, and washer, lock washer,
and nut under the scale frame. (B3)
8. Attach cross braces to the legs using
1/2—13 X 1 1/4" grade 8 bolts and
flange nuts. (B4) NOTE: THEY MAY
BE PLACED IN ANY OF THE
AVAILBLE POSITIONS TO MISS
ASSOCIATED EQUIPMENT.
9. Assemble extension ring or rings
using 3/8 X 1 1/4" grade 5 bolts with
flange nuts. (B6)
10. Assemble seed ladder to extension
rings if one was ordered using 3/8 X
1 1/4" grade 5 bolts and flange nuts.
(B5)
11. Inspect seed hopper thoroughly for
screws, bolts, fittings, etc. which may
have come loose in shipping.
12. Using a fork lift and the forklift
pockets on the weigh hopper raise it
and CAREFULLY set it on the legs
and bolt together with 5/8 X 11 X 2.0"
grade 5 bolts with a washer under the
head of the bolt, and washer, lock
washer and nut under the leg flange.
13. When the hopper is in it's final
position, anchor the floor mounts to
the floor with 1/2 - 13 X 7 1/2"
concrete anchor bolts.
14. After bolting to the floor, run load cell
cables to the summing box (field
located).
DO NOT SHORTEN THE
CABLES. ALL CABLES MUST
STAY THE SAME LENGTH.
Page 18
WEIGH HOPPERS & SURGE HOPPERS
WEIGH HOPPER SET-UP
Drawing A-6
B5
B6
B7
B4
B3
B2
B1