6
Maintenance
To prevent potential problems and comply with radiation regulations, VEGA
recommends the following maintenance schedule.
6.1 Periodic Maintenance Schedule
Description
Location
Mounting brackets
and hardware
Tags and labels
General
cleanliness
Corrosion or
rusting
Painting
Source holder
shutter check ON/
OFF Mechanism
(On applicable
source holders)
Source wipe/Leak
test
39089-US-210509
Frequency
Annually
Annually
Annually
Annually
Annually
As needed
Every six months unless
otherwise required by
applicable nuclear
regulatory agency
Every three years unless
otherwise required by
applicable nuclear
regulatory agency
Procedure
Ensure that the source holder is in the
correct location. If the source is not in
the correct location, contact your
regulatory agency immediately.
Check for loose mounting hardware.
Make certain the tags and labels are in
place and legible.
Make certain there is no buildup of dirt
or process material on operating
handles or cables.
Check the housing and operating
handle.
Clean and paint as necessary. Do not
paint labels.
See the Shutter (ON/OFF)
Mechanism procedure.
See the Leak Test procedure.
Maintenance