Siemens SICAM 7XV5673 Product Information page 19

Hide thumbs Also See for SICAM 7XV5673:
Table of Contents

Advertisement

Before commissioning the device, check that all con-
nections are made properly.
Connect the protective grounding terminal H
the protective conductor of the switch panel or of the
control cabinet.
Before commissioning the device, leave it in the final
operating room for at least 2 hours. This allows it to
reach room temperature and to prevent dampness
and condensation.
8.4
Commissioning
Before you switch on the supply voltage, verify that the
operational data match the rated data on the name
plate and the technical data as in Chapter 15. This
refers to the supply voltage U
power consumption P
After an operating time of approximately 15 min, the
device will stay within the tolerances specified in the
technical data.
The delivery includes a battery that powers the battery-
buffered memory and the real-time clock.
SICAM I/O Unit 7XV5673, Product Information
E50417-B1050-C484-A3, Edition: 03.2012
and the maximum
H
of the
device.
H
to
19