Installing the base foot
Installing module supports

5.2 Module installation, load redistribution and ballast

Installing the module
Subjects excepted. Illustrations are exemplary and may vary from the original.
V3.3 - April 2020/ASc,
Copyright BayWa r.e. Solar Energy Systems GmbH
Insert the component into the base trough on one
side as shown and then click into the base trough. If
a base foot is located above an elongated hole, it
must always be secured with a screw.
Prior to installation, the position (installation axis) of
the components must be determined on the base
trough.
Depending on the conditions on site, it's
recommended to use the mounting and removal
tool.
Insert the component into the base trough on one
side as shown and then click into the base trough.
Installation module support east-west regarding MV
6.
Prior to installation, the position (installation axis) of
the components must be determined on the base
trough.
Depending on the conditions on site, it's
recommended to use the mounting and removal
tool.
Place the module landscape on the base feet and
put it on the module support set afterwards.
Please see MV 7 for further information regarding
module installation for east-west II.
Connect the cables of adjacent modules while
installing them.
Place the string cables first.